Davis-Bacon
NJ20260001 (Rev 1)
Coverage: New Jersey • Atlantic, Burlington, Camden +7.
Published: Jan 30, 2026
Status: Active
Standard: Yes
Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| Bricklayer | $45.20 | $33.26 |
| Cement mason | $45.20 | $33.26 |
| Carpenter | $57.42 | $59.25 |
| Piledriver | $46.73 | $41.69 |
| Dock Builder & Piledrivermen | $52.98 | $52.44 |
| Line construction: Continuous pipe-type underground oil-filled transmission conduit installations: Ground person; truck with winch operator | $49.47 | $64.75 |
| Line technician; cable splicer; heavy equipment operator | $61.84 | $64.75 |
| All other work: Ground person; truck with winch operator | $49.47 | $64.75 |
| ELECTRICIAN Cable Splicer | $63.82 | $65.80 |
| Electrician | $61.84 | $65.20 |
| Electrician and cable splicer | $55.05 | $77.77 |
| Line construction: Groundmen | $30.88 | $61.32 |
| Heavy equipment operator | $46.12 | $61.32 |
| Lineman | $57.65 | $61.32 |
| Electrician & Cable Splicer | $57.70 | $45.92 |
| rground oil-filled transmission conduit installations: Electrical installation equipment operators: Hole- digging equipment; truck with winch or pole, and steel hand; truck without winch; ground person | $30.30 | $20.60 |
| Equipment service person | $53.12 | $38.81 |
| Line technician, cable splicer, x-ray technician, and equipment repair person | $53.35 | $38.81 |
| Line technician/welder | $53.35 | $38.81 |
| All other work: Ground person | $37.35 | $27.17 |
| Line technician, cable splicer, and equipment operator | $53.35 | $38.81 |
| Power equipment operators: GROUP 1 | $61.72 | $37.50 |
| GROUP 2 | $60.13 | $37.50 |
| GROUP 3 | $58.22 | $37.50 |
| GROUP 4 | $56.59 | $37.50 |
| GROUP 5 | $52.88 | $37.50 |
| GROUP 6 | $63.54 | $37.50 |
| Power equipment operators: Steel erection: GROUP 1 | $70.24 | $37.50 |
| GROUP 2 | $68.58 | $37.50 |
| GROUP 3 | $61.29 | $37.50 |
| GROUP 4 | $58.63 | $37.50 |
| GROUP 5 | $57.10 | $37.50 |
| GROUP 6 | $53.34 | $37.50 |
| GROUP 7 | $65.74 | $37.50 |
| Ironworkers: Reinforcing | $49.94 | $50.32 |
| Structural | $52.24 | $50.32 |
| Ironworker | $54.24 | $40.40 |
| Ironworkers: HIGHWAY CONSTRUCTION: Fence and guardrail | $51.77 | $39.65 |
| Precast and structural | $54.24 | $40.40 |
| Reinforced concrete | $53.24 | $40.40 |
| Laborers: Group 1 | $50.95 | $38.53 |
| Group 2 | $51.65 | $38.53 |
| Group 3 | $51.90 | $38.53 |
| Group 4 | $55.45 | $38.53 |
| Laborers: HIGHWAY CONSTRUCTION: ASPHALT WORK: GROUP 1 | $50.95 | $38.53 |
| Painters: Work on bridges (all bridges that span major waterways, railroad bridges, bridges over canyons, overpasses) | $59.29 | $33.56 |
| Painters: All other work: Brush and roller | $45.55 | $29.86 |
| Spray | $45.55 | $29.86 |
| Cement mason | $53.21 | $33.72 |
| Cement mason | $53.21 | $33.42 |
| Cement mason | $49.57 | $37.06 |
| Truck drivers: GROUP 2 | $48.23 | $25.97 |
| GROUP 3 | $48.23 | $25.97 |
| GROUP 4 | $48.58 | $25.97 |
| GROUP 5 | $48.58 | $25.97 |
| Truck drivers: Group 1 | $48.88 | $42.65 |
| Group 2 | $48.78 | $42.65 |
| Group 3 | $48.68 | $42.65 |
| Group 4 | $48.63 | $42.65 |
| Truck drivers: GROUP 2 | $44.30 | $34.11 |
| GROUP 3 | $44.45 | $34.11 |
| GROUP 4 | $44.65 | $34.11 |
| GROUP 5 | $44.80 | $34.11 |
Related Wage Determinations
View directory →Davis-Bacon
NJ20260027 (Rev 1)
New Jersey • Burlington
Davis-Bacon
NJ20260035 (Rev 1)
New Jersey • Mercer
Davis-Bacon
NJ20260048 (Rev 1)
New Jersey • Burlington
Davis-Bacon
NJ20260002 (Rev 1)
New Jersey • Bergen, Essex, Hudson +8
Davis-Bacon
NJ20260055 (Rev 1)
New Jersey • Hunterdon
Davis-Bacon
NJ20260034 (Rev 1)
New Jersey • Hunterdon