OccupationBaseFringe
Bricklayer$49.60$37.96
Bricklayer$43.56$32.50
CEMENT MASON$49.60$37.96
CEMENT MASON$43.56$32.50
CARPENTER$57.42$59.25
Dock Builder & Piledrivermen$52.98$52.44
Line construction: High-tension pipe-type cable installation: Cable splicer$61.82$55.75
Ground person$33.72$55.75
Groundman$33.72$55.75
Line technician; equipment operator; x-ray technician; equipment repair person; equipment service person; hole- digging equipment operator; truck with winch or pole and steel hand; truck without winch$56.20$55.75
Line technician-welder$59.01$55.75
Groundman$38.21$62.75
Line technician-welder$66.86$62.75
Electricians: Electrician$62.90$62.50
All other work: Cable splicer$73.59$62.50
Electrician$63.82$65.80
Line construction: Continuous pipe-type underground oil-filled transmission conduit installations: Ground person; truck with winch operator$39.83$60.93
Line technician; cable splicer; heavy equipment operator$49.79$60.93
All other work: Ground person; truck with winch operator$39.83$60.93
Electricians: Cable splicer$65.35$71.25
Electrician$61.40$63.75
Line construction: Continuous pipe-type underground oil-filled transmission conduit installations: Cable splicer$59.47$67.75
Crane Operator$59.47$67.75
Groundman (when installing conduit on public roadways)$31.03$67.75
Groundman; winch operator$50.92$67.75
an; x-ray technician; equipment repair person; equipment serviceperson; electrical installation worker; hole- digging equipment operator; truck operator with winch or pole; truck operator without winch$51.71$67.75
All other work: Cable splicer$59.46$67.75
Crane Operator$58.44$67.75
Line technician$51.71$67.75
winch operator$50.92$67.75
Power equipment operators: Steel erection: GROUP 1$70.24$37.50
GROUP 2$68.58$37.50
GROUP 3$61.29$37.50
GROUP 4$58.63$37.50
GROUP 5$57.10$37.50
GROUP 6$53.34$37.50
GROUP 7$65.74$37.50
Power equipment operators: GROUP 1$61.72$37.50
GROUP 2$60.13$37.50
GROUP 3$58.22$37.50
GROUP 4$56.59$37.50
GROUP 5$52.88$37.50
GROUP 6$63.54$37.50
Ironworkers: Reinforcing$49.94$50.32
Structural$52.24$50.32
Ironworkers$34.05$24.00
Ironworker$54.24$38.40
Laborers: GROUP 1$50.95$38.53
GROUP 2$51.65$38.53
GROUP 3$51.90$38.53
GROUP 4$55.45$38.53
Laborers: ASPHALT WORK: GROUP 1$50.95$38.53
Painters: Work on bridges (all bridges that span major waterways, railroad bridges, bridges over canyons, overpasses)$59.29$33.56
Painters: All other work: Brush and roller$45.55$29.86
Spray$45.55$29.86
CEMENT MASON$54.64$30.95
Cement mason$53.21$33.42
Truck drivers: Group 1$46.61$31.82
a Group 2$46.51$31.82
a Group 3$46.41$31.82
a Group 4$45.77$31.82
Truck drivers: Group 1$48.88$42.65
Group 2$48.78$42.65
Group 3$48.68$42.65
Group 4$48.63$42.65
Truck drivers: Group 1$47.36$44.17
Group 2$47.41$44.17
Group 3$47.51$44.17
Group 4$47.61$44.17