Davis-Bacon
CA20260018 (Rev 5)
Coverage: California • Alameda, Calaveras, Contra Costa +14.
Published: May 18, 2026
Status: Active
Standard: Yes
Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| ANDLER: INCLUDES PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS FROM MECHANICAL SYSTEMS, WHETHER THEY CONTAIN ASBESTOS OR NOT (AREA 2) | $44.73 | $12.75 |
| ASBESTOS WORKERS/INSULATOR: INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS, AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS (AREA 2) | $64.56 | $25.07 |
| ASBESTOS WORKERS/INSULATOR: INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS, AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS (AREA 1) | $84.76 | $25.07 |
| BOILERMAKER: (AREA 2) | $45.60 | $38.99 |
| BOILERMAKER: (AREA 1) | $49.62 | $41.27 |
| MARBLE FINISHER | $42.06 | $19.80 |
| MARBLE MASON | $61.72 | $30.31 |
| BRICKLAYER (8) ALAMEDA, CONTRA COSTA, SAN BENITO, SANTA CLARA) | $56.94 | $26.28 |
| BRICKLAYER (16) MONTEREY, SANTA CRUZ | $54.18 | $27.82 |
| BRICKLAYER ( 9) CALAVERAS, SAN JOAQUIN, STANISLAUS, TOULUMNE | $52.76 | $25.01 |
| BRICKLAYER ( 7) SAN FRANCISCO, SAN MATEO | $57.02 | $28.50 |
| BRICKLAYER ( 1) FRESNO, KINGS, MADERA, MARIPOSA, MERCED | $51.17 | $25.80 |
| TERRAZZO WORKER/SETTER | $60.58 | $29.79 |
| TERRAZZO FINISHER | $44.93 | $20.98 |
| TILE LAYER AREA 3 | $50.28 | $22.05 |
| TILE LAYER AREA 2 | $55.17 | $22.52 |
| TILE LAYER AREA 1 | $59.92 | $22.62 |
| TILE FINISHER AREA 3 | $32.68 | $18.32 |
| TILE FINISHER AREA 2 | $34.76 | $19.22 |
| TILE FINISHER AREA 1 | $37.75 | $19.28 |
| CARPENTERS: MILLWRIGHT (SAN FRANCISCO COUNTY) | $60.49 | $35.11 |
| CARPENTERS: JOURNEYMAN CARPENTER (SAN FRANCISCO COUNTY) | $60.39 | $33.52 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER (SAN FRANCISCO COUNTY) | $60.54 | $33.52 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER (SAN FRANCISCO COUNTY) | $60.39 | $33.52 |
| F CLASSIFICATIONS: EMPLOYEES WORKING IN ANY COMBINATION OF CLASSIFICATIONS WITHIN THE DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE FOR THAT SHIFT | $59.51 | $34.69 |
| F CLASSIFICATIONS: EMPLOYEES WORKING IN ANY COMBINATION OF CLASSIFICATIONS WITHIN THE DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE FOR THAT SHIFT | $64.51 | $34.69 |
| F CLASSIFICATIONS: EMPLOYEES WORKING IN ANY COMBINATION OF CLASSIFICATIONS WITHIN THE DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE FOR THAT SHIFT | $103.62 | $34.69 |
| F CLASSIFICATIONS: EMPLOYEES WORKING IN ANY COMBINATION OF CLASSIFICATIONS WITHIN THE DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE FOR THAT SHIFT | $60.51 | $34.69 |
| F CLASSIFICATIONS: EMPLOYEES WORKING IN ANY COMBINATION OF CLASSIFICATIONS WITHIN THE DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE FOR THAT SHIFT | $54.10 | $34.69 |
| PILEDRIVER | $54.10 | $34.69 |
| MASTER INSTALLER (MODULAR FURNITURE INSTALLER) AREA 3 | $31.38 | $23.03 |
| MASTER INSTALLER (MODULAR FURNITURE INSTALLER) AREA 2 | $32.71 | $23.03 |
| MASTER INSTALLER (MODULAR FURNITURE INSTALLER) AREA 1 | $36.43 | $23.03 |
| INSTALLER (MODULAR FURNITURE INSTALLER) AREA 3 | $25.16 | $22.53 |
| INSTALLER (MODULAR FURNITURE INSTALLER) AREA 2 | $26.11 | $22.53 |
| INSTALLER (MODULAR FURNITURE INSTALLER) AREA 1 | $28.76 | $22.53 |
| DRYWALL STOCKER/SCRAPPER: (AREA 4) | $22.97 | $18.22 |
| DRYWALL STOCKER/SCRAPPER: (AREA 3) | $23.64 | $18.22 |
| DRYWALL STOCKER/SCRAPPER: (AREA 2) | $23.39 | $18.22 |
| DRYWALL STOCKER/SCRAPPER: (AREA 1) | $26.33 | $18.22 |
| DRYWALL INSTALLERS/LATHERS:: (AREA 4) | $45.92 | $31.26 |
| DRYWALL INSTALLERS/LATHERS:: (AREA 3) | $47.27 | $31.26 |
| DRYWALL INSTALLERS/LATHERS:: (AREA 2) | $46.77 | $31.26 |
| DRYWALL INSTALLERS/LATHERS:: (AREA 1) | $52.65 | $31.26 |
| CARPENTERS: MILLWRIGHT (CONTRA COSTA COUNTY) | $52.75 | $32.41 |
| CARPENTERS: JOURNEYMAN CARPENTER (CONTRA COSTA COUNTY) | $52.65 | $30.82 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER (CONTRA COSTA COUNTY) | $52.80 | $30.82 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER (CONTRA COSTA COUNTY) | $52.65 | $30.82 |
| CARPENTERS: MILLWRIGHT (SAN JOAQUIN COUNTY) | $49.27 | $32.41 |
| CARPENTERS: JOURNEYMAN CARPENTER (SAN JOAQUIN COUNTY) | $46.77 | $30.82 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER (SAN JOAQUIN COUNTY) | $46.92 | $30.82 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER (SAN JOAQUIN COUNTY) | $52.65 | $30.82 |
| CARPENTERS: MILLWRIGHT (CALAVERAS, MARIPOSA, MERCED, STANISLAUS AND TUOLUMNE COUNTIES) | $47.92 | $32.41 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER CALAVERAS, MARIPOSA, MERCED, STANISLAUS AND TUOLUMNE COUNTIES | $45.57 | $30.82 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER (CALAVERAS, MARIPOSA, MERCED, STANISLAUS AND TUOLUMNE COUNTIES) | $52.65 | $30.82 |
| CARPENTERS: MILLWRIGHT (SAN MATEO COUNTY) | $60.49 | $35.11 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER (SAN MATEO COUNTY) | $60.54 | $33.52 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER (SAN MATEO COUNTY) | $60.39 | $33.52 |
| CARPENTERS: MILLWRIGHT (SANTA CLARA COUNTY) | $54.95 | $33.08 |
| CARPENTERS: JOURNEYMAN CARPENTER (SANTA CLARA COUNTY) | $54.85 | $31.49 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER (SANTA CLARA COUNTY) | $55.00 | $31.49 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER (SANTA CLARA COUNTY) | $54.85 | $31.49 |
| CARPENTERS: MILLWRIGHT (SAN BENITO COUNTY) | $51.47 | $33.08 |
| CARPENTERS: JOURNEYMAN CARPENTER (SAN BENITO COUNTY) | $48.97 | $31.49 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER (SAN BENITO COUNTY) | $49.12 | $31.49 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER (SAN BENITO COUNTY) | $54.85 | $31.49 |
| CARPENTERS: MILLWRIGHT (SANTA CRUZ COUNTY) | $51.47 | $33.08 |
| CARPENTERS: JOURNEYMAN CARPENTER (SANTA CRUZ COUNTY) | $48.97 | $31.49 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER (SANTA CRUZ COUNTY) | $49.12 | $31.49 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER (SANTA CRUZ COUNTY) | $54.85 | $31.49 |
| CARPENTERS: MILLWRIGHT (MONTEREY COUNTY) | $51.47 | $33.08 |
| CARPENTERS: JOURNEYMAN CARPENTER (MONTEREY COUNTY) | $48.97 | $31.49 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER (MONTEREY COUNTY) | $49.12 | $31.49 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER (MONTEREY COUNTY) | $54.85 | $31.49 |
| CARPENTERS: JOURNEYMAN CARPENTER (FRESNO AND MADERA COUNTIES) | $47.62 | $31.49 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER (FRESNO AND MADERA COUNTIES) | $47.77 | $31.49 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER (FRESNO AND MADERA COUNTIES) | $54.85 | $31.49 |
| CARPENTERS: MILLWRIGHT (ALAMEDA COUNTY) | $54.95 | $33.08 |
| CARPENTERS: JOURNEYMAN CARPENTER (ALAMEDA COUNTY) | $54.85 | $31.49 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER (ALAMEDA COUNTY) | $55.00 | $31.49 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER (ALAMEDA COUNTY) | $54.85 | $31.49 |
| CARPENTERS: MILLWRIGHT (KINGS COUNTY) | $50.12 | $33.08 |
| CARPENTERS: JOURNEYMAN CARPENTER (KINGS COUNTY) | $47.62 | $31.49 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER KINGS COUNTY | $47.77 | $31.49 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER (KINGS COUNTY) | $54.85 | $31.49 |
| ING), ON PROJECTS WHICH INVOLVE NEW OR MAJOR REMODEL BUILDING CONSTRUCTION, FOR WHICH THE CONDUCTORS FOR THE FIRE ALARM SYSTEM ARE INSTALLED IN THE CONDUIT, SHALL BE PERFORMED BY THE INSIDE ELECTRICIAN | $67.65 | $31.78 |
| INVOLVE NEW OR MAJOR REMODEL BUILDING CONSTRUCTION, FOR WHICH THE CONDUCTORS FOR THE FIRE ALARM SYSTEM ARE INSTALLED IN THE CONDUIT, SHALL BE PERFORMED BY THE INSIDE ELECTRICIAN.(SAN FRANCISCO COUNTY) | $58.83 | $31.51 |
| ELECTRICIAN (SAN FRANCISCO COUNTY) | $91.25 | $48.05 |
| ELECTRICIAN (FRESNO, KINGS, AND MADERA COUNTIES) | $50.00 | $30.15 |
| E, WHEN EITHER OF THE FOLLOWING TWO (2) CONDITIONS APPLY: 1. THE PROJECT INVOLVES NEW OR MAJOR REMODEL BUILDING TRADES CONSTRUCTION. 2. THE CONDUCTORS FOR THE FIRE ALARM SYSTEM ARE INSTALLED IN CONDUIT | $52.07 | $28.21 |
| E, WHEN EITHER OF THE FOLLOWING TWO (2) CONDITIONS APPLY: 1. THE PROJECT INVOLVES NEW OR MAJOR REMODEL BUILDING TRADES CONSTRUCTION. 2. THE CONDUCTORS FOR THE FIRE ALARM SYSTEM ARE INSTALLED IN CONDUIT | $45.28 | $28.01 |
| Z, MONTEREY, AND SAN BENITO COUNTIES WITHIN 25 AIR MILES OF HIGHWAY 1 AND DOLAN ROAD IN MOSS LANDING, AND AN AREA EXTENDING 5 MILES EAST AND WEST OF HIGHWAY 101 SOUTH TO THE SAN LUIS OBISPO COUNTY LINE | $70.41 | $33.76 |
| ELECTRICIAN (MONTEREY, SAN BENITO AND SANTA CRUZ COUNTIES) ZONE B: ANY AREA OUTSIDE OF ZONE A | $77.45 | $33.97 |
| ING), ON PROJECTS WHICH INVOLVE NEW OR MAJOR REMODEL BUILDING CONSTRUCTION, FOR WHICH THE CONDUCTORS FOR THE FIRE ALARM SYSTEM ARE INSTALLED IN THE CONDUIT, SHALL BE PERFORMED BY THE INSIDE ELECTRICIAN | $55.12 | $24.30 |
| SOUND & COMMUNICATIONS, INSTALLER (MONTEREY, SAN BENITO, AND SANTA CRUZ COUNTIES) | $47.93 | $24.09 |
| ELECTRICIAN (CONTRA COSTA COUNTY) | $66.26 | $35.84 |
| CABLE SPLICER (CONTRA COSTA COUNTY) | $74.54 | $36.09 |
| ING), ON PROJECTS WHICH INVOLVE NEW OR MAJOR REMODEL BUILDING CONSTRUCTION, FOR WHICH THE CONDUCTORS FOR THE FIRE ALARM SYSTEM ARE INSTALLED IN THE CONDUIT, SHALL BE PERFORMED BY THE INSIDE ELECTRICIAN | $61.04 | $31.08 |
| ING), ON PROJECTS WHICH INVOLVE NEW OR MAJOR REMODEL BUILDING CONSTRUCTION, FOR WHICH THE CONDUCTORS FOR THE FIRE ALARM SYSTEM ARE INSTALLED IN THE CONDUIT, SHALL BE PERFORMED BY THE INSIDE ELECTRICIAN | $53.08 | $30.84 |
| OUND OR SUPPORTING STRUCTURES: TO BE PAID ONE AND ONE-HALF TIMES THE STRAIGHT-TIME RATE OF PAY. WORK ON STRUCTURES OF 60 FT. OR OVER (AS DESCRIBED ABOVE): TO BE PAID TWICE THE STRAIGHT-TIME RATE OF PAY | $91.03 | $49.05 |
| OUND OR SUPPORTING STRUCTURES: TO BE PAID ONE AND ONE-HALF TIMES THE STRAIGHT-TIME RATE OF PAY. WORK ON STRUCTURES OF 60 FT. OR OVER (AS DESCRIBED ABOVE): TO BE PAID TWICE THE STRAIGHT-TIME RATE OF PAY | $104.68 | $49.46 |
| ING), ON PROJECTS WHICH INVOLVE NEW OR MAJOR REMODEL BUILDING CONSTRUCTION, FOR WHICH THE CONDUCTORS FOR THE FIRE ALARM SYSTEM ARE INSTALLED IN THE CONDUIT, SHALL BE PERFORMED BY THE INSIDE ELECTRICIAN | $67.08 | $31.26 |
| ING), ON PROJECTS WHICH INVOLVE NEW OR MAJOR REMODEL BUILDING CONSTRUCTION, FOR WHICH THE CONDUCTORS FOR THE FIRE ALARM SYSTEM ARE INSTALLED IN THE CONDUIT, SHALL BE PERFORMED BY THE INSIDE ELECTRICIAN | $58.33 | $31.00 |
| ELECTRICIAN (ALAMEDA COUNTY) | $76.00 | $49.07 |
| CABLE SPLICER (ALAMEDA COUNTY) | $87.40 | $49.41 |
| ELECTRICIAN: (2) ALL OTHER WORK (CALAVERAS AND SAN JOAQUIN COUNTIES) | $49.45 | $31.96 |
| ELECTRICIAN: (1) TUNNEL WORK (CALAVERAS AND SAN JOAQUIN COUNTIES) | $51.92 | $32.04 |
| CABLE SPLICER (CALAVERAS AND SAN JOAQUIN COUNTIES) | $59.34 | $32.26 |
| SOUND & COMMUNICATIONS: INSTALLER (ALAMEDA COUNTY) | $58.33 | $31.00 |
| ING), ON PROJECTS WHICH INVOLVE NEW OR MAJOR REMODEL BUILDING CONSTRUCTION, FOR WHICH THE CONDUCTORS FOR THE FIRE ALARM SYSTEM ARE INSTALLED IN THE CONDUIT, SHALL BE PERFORMED BY THE INSIDE ELECTRICIAN | $52.07 | $28.21 |
| ING), ON PROJECTS WHICH INVOLVE NEW OR MAJOR REMODEL BUILDING CONSTRUCTION, FOR WHICH THE CONDUCTORS FOR THE FIRE ALARM SYSTEM ARE INSTALLED IN THE CONDUIT, SHALL BE PERFORMED BY THE INSIDE ELECTRICIAN | $45.28 | $28.01 |
| ELECTRICIAN (SAN MATEO COUNTY) | $86.00 | $51.07 |
| OF JOURNEYMAN ELECTRICIAN | $48.50 | $30.09 |
| tes Fringes LINE CONSTRUCTION: (3) GROUNDMAN HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DAY AFTER THANKSGIVING, CHRISTMAS DAY | $40.76 | $21.76 |
| D & UNDERGROUND DISTRIBUTION LINE EQUIPMENT) HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DAY AFTER THANKSGIVING, CHRISTMAS DAY | $53.30 | $22.26 |
| INE CONSTRUCTION: (1) LINEMAN; CABLE SPLICER HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DAY AFTER THANKSGIVING, CHRISTMAS DAY | $70.16 | $24.71 |
| FOR 6 MONTHS TO 5 YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS' DAY, THANKSGIVING DAY, FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY | $84.05 | $38.44 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 6 | $42.50 | $31.15 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 5 | $44.73 | $31.15 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 4 | $47.37 | $31.15 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 3 (Truck Crane Oiler) | $45.12 | $31.15 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 3 (Oiler) | $42.89 | $31.15 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 3 (Lifting devices) | $49.14 | $31.15 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 2 (Truck Crane Oiler) | $45.41 | $31.15 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 2 (Oiler) | $43.11 | $31.15 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 2 (Lifting devices) | $50.82 | $31.15 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 1 (Truck Crane Oiler) | $45.66 | $31.15 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 1 (Oiler) | $43.38 | $31.15 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 1 (Lifting devices) | $52.64 | $31.15 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 5) | $58.09 | $32.53 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 4) | $59.23 | $32.53 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 3) | $60.37 | $32.53 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 2) | $61.70 | $32.53 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 1-A) | $65.43 | $32.53 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 1) | $62.96 | $32.53 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 5) | $58.19 | $32.53 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 4) | $59.33 | $32.53 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 3) | $60.47 | $32.53 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 2) | $61.80 | $32.53 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 1) | $63.06 | $32.53 |
| OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 5 | $62.24 | $32.53 |
| OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 4 | $63.54 | $32.53 |
| OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 3 | $65.56 | $32.53 |
| OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 2 | $67.04 | $32.53 |
| OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 1 | $68.81 | $32.53 |
| OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 4 | $61.30 | $32.53 |
| OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 3 (Hydraulic) | $59.98 | $32.53 |
| OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 3 (Cranes) | $64.34 | $32.53 |
| OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 2 | $66.08 | $32.53 |
| OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 1 | $68.59 | $32.53 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 8-A | $55.49 | $32.53 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 8 | $57.70 | $32.53 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 7 | $58.84 | $32.53 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 6 | $59.98 | $32.53 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 5 | $61.30 | $32.53 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 4 | $62.57 | $32.53 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 3 | $63.95 | $32.53 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 2 | $65.43 | $32.53 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 1 | $66.96 | $32.53 |
| Y COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART | $53.23 | $39.55 |
| Y COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART | $56.53 | $39.55 |
| Y COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART | $57.65 | $39.55 |
| Y COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART | $62.61 | $39.55 |
| Y COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART | $51.23 | $39.55 |
| Y COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART | $54.53 | $39.55 |
| Y COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART | $60.61 | $39.55 |
| Y COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART | $55.65 | $39.55 |
| OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY: GROUP 3 (AREA 2) | $49.64 | $28.56 |
| OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY: GROUP 3 (AREA 1) | $47.64 | $28.56 |
| OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY: GROUP 2 (AREA 2) | $54.25 | $28.56 |
| OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY: GROUP 2 (AREA 1) | $52.25 | $28.56 |
| OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY: GROUP 1 (AREA 2) | $57.85 | $28.56 |
| OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY: GROUP 1 (AREA 1) | $55.85 | $28.56 |
| IRONWORKERS: ORNAMENTAL, REINFORCING AND STRUCTURAL (ALAMEDA, CONTRA COSTA, SAN MATEO, SANTA CLARA COUNTIES) | $55.33 | $35.15 |
| IRONWORKERS: FENCE ERECTOR (ALAMEDA, CONTRA COSTA, SAN MATEO, SANTA CLARA COUNTIES) | $45.78 | $26.51 |
| IRONWORKERS: ORNAMENTAL, REINFORCING AND STRUCTURAL (SAN FRANCISCO CITY AND COUNTY) | $55.83 | $35.15 |
| IRONWORKERS: FENCE ERECTOR (SAN FRANCISCO CITY AND COUNTY) | $45.78 | $26.51 |
| IRONWORKER: ORNAMENTAL, REINFORCING AND STRUCTURAL (REMAINING COUNTIES) | $50.70 | $35.15 |
| IRONWORKER: FENCE ERECTOR (REMAINING COUNTIES) | $45.78 | $26.51 |
| LABORER, ASBESTOS/MOLD/LEAD LABORER: AREA 2 | $38.15 | $30.03 |
| LABORER, ASBESTOS/MOLD/LEAD LABORER: AREA 1 | $39.15 | $30.03 |
| ges LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON II INSTALLATION AND REMOVAL OF TEMPORARY/PERMANENT SIGNS, MARKERS, DELINEATORS AND CRASH CUSHIONS. (CALAVERAS AND SAN JOAQUIN COUNTIES) | $34.06 | $27.30 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON I LAYOUT OF TRAFFIC CONTROL, CRASH CUSHIONS, CONSTRUCTION AREA AND ROADSIDE SIGNAGE. (CALAVERAS AND SAN JOAQUIN COUNTIES) | $36.56 | $27.30 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: ESCORT DRIVER, FLAG PERSON (CALAVERAS AND SAN JOAQUIN COUNTIES) | $36.26 | $27.30 |
| LABORER: MASON TENDER-BRICK (SAN JOAQUIN COUNTY) | $36.29 | $25.55 |
| TUNNEL AND SHAFT LABORERS: SHOTCRETE SPECIALIST | $46.41 | $27.72 |
| TUNNEL AND SHAFT LABORERS: GROUP 5 GROUT CREW; REBOUNDMAN; SWAMPER/ BRAKEMAN | $44.42 | $27.72 |
| TUNNEL AND SHAFT LABORERS: GROUP 4 VIBRATOR OPERATOR, PAVEMENT BREAKER; BULL GANG - MUCKERS, TRACKMEN; CONCRETE CREW - INCLUDES RODDING AND SPREADING, DUMPMEN (ANY METHOD) | $44.96 | $27.72 |
| CK HAULER, STEEL FORM RAISER AND SETTER; TIMBERMAN, RETIMBERMAN (WOOD OR STEEL OR SUBSTITUTE MATERIALS THEREFORE); TUGGER (FOR TUNNEL LABORER WORK); CABLE TENDER; CHUCK TENDER; POWDERMAN - PRIMER HOUSE | $45.41 | $27.72 |
| TUNNEL AND SHAFT LABORERS: GROUP 2 RODMEN; SHAFT WORK & RAISE (BELOW ACTUAL OR EXCAVATED GROUND LEVEL) | $45.66 | $27.72 |
| TUNNEL AND SHAFT LABORERS: GROUP 1 DIAMOND DRILLER; GROUNDMEN; GUNITE AND SHOTCRETE NOZZLEMEN | $45.89 | $27.72 |
| LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS (CALAVERAS AND SAN JOAQUIN COUNTIES)- (2) Establishment Warranty Period | $31.59 | $29.89 |
| LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS (CALAVERAS AND SAN JOAQUIN COUNTIES)- (1) New Construction | $37.90 | $29.89 |
| PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | $38.00 | $29.89 |
| LABORER, WRECKING: GROUP 1 (CALAVERAS AND SAN JOAQUIN COUNTIES) | $38.15 | $29.89 |
| PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | $37.90 | $29.89 |
| PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | $38.02 | $29.89 |
| PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | $38.61 | $29.89 |
| LABORER, GUNITE: GROUP 1 (CALAVERAS AND SAN JOAQUIN COUNTIES) | $39.11 | $29.89 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $31.59 | $29.89 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $37.90 | $29.89 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $38.00 | $29.89 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $38.70 | $29.89 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $38.20 | $29.89 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $38.37 | $29.89 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $38.15 | $29.89 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $38.85 | $29.89 |
| LABORER (CONSTRUCTION CRAFT LABORERS) GROUP 1-f CALAVERAS AND SAN JOAQUIN COUNTIES | $30.37 | $29.89 |
| PER HOUR ADDITIONAL | $39.77 | $28.54 |
| s LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON II INSTALLATION AND REMOVAL OF TEMPORARY/PERMANENT SIGNS, MARKERS, DELINEATORS AND CRASH CUSHIONS. (SAN FRANCISCO AND SAN MATEO COUNTIES) | $35.06 | $27.30 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON I LAYOUT OF TRAFFIC CONTROL, CRASH CUSHIONS, CONSTRUCTION AREA AND ROADSIDE SIGNAGE. (SAN FRANCISCO AND SAN MATEO COUNTIES) | $37.56 | $27.30 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: ESCORT DRIVER, FLAG PERSON (SAN FRANCISCO AND SAN MATEO COUNTIES) | $37.26 | $27.30 |
| TUNNEL AND SHAFT LABORERS: SHOTCRETE SPECIALIST (SAN FRANCISCO AND SAN MATEO COUNTIES) | $46.41 | $27.72 |
| TUNNEL AND SHAFT LABORERS: GROUP 5 GROUT CREW; REBOUNDMAN; SWAMPER/ BRAKEMAN (SAN FRANCISCO AND SAN MATEO COUNTIES) | $44.42 | $27.72 |
| D SHAFT LABORERS: GROUP 4 VIBRATOR OPERATOR, PAVEMENT BREAKER; BULL GANG - MUCKERS, TRACKMEN; CONCRETE CREW - INCLUDES RODDING AND SPREADING, DUMPMEN (ANY METHOD) (SAN FRANCISCO AND SAN MATEO COUNTIES) | $44.96 | $27.72 |
| TIMBERMAN, RETIMBERMAN (WOOD OR STEEL OR SUBSTITUTE MATERIALS THEREFORE); TUGGER (FOR TUNNEL LABORER WORK); CABLE TENDER; CHUCK TENDER; POWDERMAN - PRIMER HOUSE (SAN FRANCISCO AND SAN MATEO COUNTIES) | $45.41 | $27.72 |
| TUNNEL AND SHAFT LABORERS: GROUP 2 RODMEN; SHAFT WORK & RAISE (BELOW ACTUAL OR EXCAVATED GROUND LEVEL) (SAN FRANCISCO AND SAN MATEO COUNTIES) | $45.66 | $27.72 |
| TUNNEL AND SHAFT LABORERS: GROUP 1 DIAMOND DRILLER; GROUNDMEN; GUNITE AND SHOTCRETE NOZZLEMEN (SAN FRANCISCO AND SAN MATEO COUNTIES) | $45.89 | $27.72 |
| LABORERS:, GUNITE - AREA A:: GROUP 1 (SAN FRANCISCO, AND SAN MATEO COUNTIES) | $37.46 | $27.30 |
| PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | $36.25 | $27.30 |
| PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | $36.37 | $27.30 |
| PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | $36.96 | $27.30 |
| LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA A: (SAN FRANCISCO, AND SAN MATEO COUNTIES)- (2) Establishment Warranty Period | $29.94 | $27.30 |
| LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA A: (SAN FRANCISCO, AND SAN MATEO COUNTIES)- (1) New Construction | $36.25 | $27.30 |
| LABORER, WRECKING - AREA A:: GROUP 1 (SAN FRANCISCO, AND SAN MATEO COUNTIES) | $36.50 | $27.30 |
| PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | $36.35 | $27.30 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $29.94 | $27.30 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $36.25 | $27.30 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $36.35 | $27.30 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $37.05 | $27.30 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $36.55 | $27.30 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $36.72 | $27.30 |
| ED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $36.50 | $27.30 |
| ERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | $37.20 | $27.30 |
| PER DAY ADDITIONAL | $37.05 | $27.45 |
| PER HOUR ADDITIONAL | $41.93 | $30.32 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON II (Area B) | $34.06 | $27.30 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON II (Area A) | $35.06 | $27.30 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON I (Area B) | $36.56 | $27.30 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON I (Area A) | $37.56 | $27.30 |
Related Wage Determinations
View directory →Davis-Bacon
CA20260009 (Rev 1)
California • Fresno, Kern, Madera +4
Davis-Bacon
CA20260026 (Rev 3)
California • San Bernardino
Davis-Bacon
CA20260002 (Rev 3)
California • Imperial
Davis-Bacon
CA20260016 (Rev 3)
California • Tulare
Davis-Bacon
CA20260015 (Rev 3)
California • Ventura
Davis-Bacon
CA20260008 (Rev 1)
California • Butte