Asbestos Workers/Insulator (Includes the application of all insulating materials, Protective Coverings, Coatings, and Finishes to all types of mechanical systems) Area 1$84.76$25.07
Area 2$64.56$25.07
handler (Includes preparation, wetting, stripping, removal, scrapping, vacuuming, bagging and disposing of all insulation materials from mechanical systems, whether they contain asbestos or not) AREA 1$35.31$12.75
AREA 2$44.73$12.75
Remaining Counties$45.60$38.99
MARBLE FINISHER$42.06$19.80
BRICKLAYER AREA 1$52.76$25.01
AREA 2$57.02$28.50
TERRAZZO FINISHER$44.93$20.98
TERRAZZO WORKER/SETTER$60.58$29.79
TILE FINISHER Area 1$35.00$17.44
Area 2$34.76$19.22
Area 3$37.75$19.28
Area 4$35.78$19.23
Tile Layer Area 1$55.55$21.08
Area 2$55.17$22.52
Area 3$59.92$22.62
Area 4$56.79$22.54
MARBLE MASON$61.72$30.31
Diver Assistant Tender, ROV Tender/Technician$54.10$34.69
Diver standby$60.51$34.69
Diver Tender$59.51$34.69
Diver wet$103.62$34.69
Manifold Operator (mixed gas)$64.51$34.69
Piledriver$54.10$34.69
Drywall Installers/Lathers: Area 1$52.65$31.26
Area 3$47.27$31.26
Area 4$45.92$31.26
Drywall Stocker/Scrapper Area 1$26.33$18.22
Area 3$23.64$18.22
Area 4$22.97$18.22
CARPENTER Bridge Builder/Highway Carpenter$52.65$30.82
Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer$52.80$30.82
Journeyman Carpenter$52.65$30.82
Millwright$52.75$32.41
Modular Furniture Installer Area 1 Installer$28.76$22.53
Lead Installer$32.21$23.03
Master Installer$36.43$23.03
Area 2 Installer$26.11$22.53
Lead Installer$29.08$23.03
Master Installer$32.71$23.03
Area 3 Installer$25.16$22.53
Lead Installer$27.96$23.03
Master Installer$31.38$23.03
Carpenters Bridge Builder/Highway Carpenter$60.39$33.52
Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer$54.66$33.52
Journeyman Carpenter$54.51$33.52
Millwright$57.01$35.11
Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer$53.31$33.52
Journeyman Carpenter$53.16$33.52
Millwright$55.66$35.11
Carpenters Bridge Builder/Highway Carpenter$52.65$30.82
Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer$45.57$30.82
Journeyman Carpenter$45.42$30.82
Millwright$47.92$32.41
Carpenters Bridge Builder/Highway Carpenter$54.85$31.49
Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer$55.00$31.49
Journeyman Carpenter$54.85$31.49
Millwright$54.95$33.08
Sound & Communications Installer$53.08$30.84
Technician$61.04$31.08
Communications System Sound & Communications Installer$40.00$25.50
Sound & Communications Technician$46.00$25.68
ELECTRICIAN Remaining area$52.70$38.68
Sierra Army Depot, Herlong$48.83$18.54
Tunnel work$41.01$18.54
ELECTRICIAN$48.50$23.04
ELECTRICIAN$59.17$32.04
ELECTRICIAN$47.04$21.84
LINE CONSTRUCTION (1) Lineman; Cable splicer$70.16$24.71
Equipment specialist (operates crawler tractors, commercial motor vehicles, backhoes, trenchers, cranes (50 tons and below), overhead & underground distribution line equipment)$53.30$22.26
Groundman$40.76$21.76
Powderman$51.87$18.79
ELEVATOR MECHANIC$84.05$38.43
Dredging: (DREDGING: CLAMSHELL & DIPPER DREDGING; HYDRAULIC SUCTION DREDGING:) AREA 1: (1) Leverman$60.61$39.55
Dredge Dozer; Heavy duty repairman$55.65$39.55
Booster Pump Operator; Deck Engineer; Deck mate; Dredge Tender; Winch Operator$54.53$39.55
Bargeman; Deckhand; Fireman; Leveehand; Oiler$51.23$39.55
AREA 2: (1) Leverman$62.61$39.55
Dredge Dozer; Heavy duty repairman$57.65$39.55
Booster Pump Operator; Deck Engineer; Deck mate; Dredge Tender; Winch Operator$56.53$39.55
Bargeman; Deckhand; Fireman; Leveehand; Oiler$53.23$39.55
OPERATOR: Power Equipment (LANDSCAPE WORK ONLY) GROUP 1 AREA 1$55.85$28.56
AREA 2$57.85$28.56
GROUP 2 AREA 1$52.25$28.56
AREA 2$54.25$28.56
GROUP 3 AREA 1$47.64$28.56
AREA 2$49.64$28.56
OPERATOR: Power Equipment (AREA 1:) GROUP 1$66.96$32.53
GROUP 2$65.43$32.53
GROUP 3$63.95$32.53
GROUP 4$62.57$32.53
GROUP 5$61.30$32.53
GROUP 6$59.98$32.53
GROUP 7$58.84$32.53
GROUP 8$57.70$32.53
GROUP 8-A$55.49$32.53
OPERATOR: Power Equipment (Cranes and Attachments - AREA 1:) GROUP 1 Cranes$68.59$32.53
Oiler$43.79$31.15
Truck crane oiler$46.08$31.15
GROUP 2 Cranes$66.08$32.53
Oiler$42.83$31.15
Truck crane oiler$45.07$31.15
GROUP 3 Cranes$64.34$32.53
Hydraulic$60.61$32.53
Oiler$42.55$31.15
Truck crane oiler$44.83$31.15
GROUP 4 Cranes$61.30$32.53
OPERATOR: Power Equipment (Piledriving - AREA 1:) GROUP 1 Lifting devices$52.64$31.15
Oiler$43.38$31.15
Truck Crane Oiler$45.66$31.15
GROUP 2 Lifting devices$50.82$31.15
Oiler$43.11$31.15
Truck Crane Oiler$45.41$31.15
GROUP 3 Lifting devices$49.14$31.15
Oiler$42.89$31.15
Truck Crane Oiler$45.12$31.15
GROUP 4 Lifting devices$47.37$31.15
GROUP 5 Lifting devices$44.73$31.15
GROUP 6 Lifting devices$42.50$31.15
OPERATOR: Power Equipment (Steel Erection - AREA 1:) GROUP 1 Cranes$68.81$32.53
Oiler$43.72$31.15
Truck Crane Oiler$45.95$31.15
GROUP 2 Cranes$67.04$32.53
Oiler$43.45$31.15
Truck Crane Oiler$45.73$31.15
GROUP 3 Cranes$65.56$32.53
Hydraulic$45.07$31.15
Oiler$43.23$31.15
Truck Crane Oiler$45.46$31.15
GROUP 4 Cranes$63.54$32.53
GROUP 5 Cranes$62.24$32.53
OPERATOR: Power Equipment (Tunnel and Underground Work - AREA 1:) SHAFTS, STOPES, RAISES: GROUP 1$63.06$32.53
GROUP 1-A$65.53$32.53
GROUP 2$61.80$32.53
GROUP 3$60.47$32.53
GROUP 4$59.33$32.53
GROUP 5$58.19$32.53
UNDERGROUND: GROUP 1$62.96$32.53
GROUP 1-A$65.43$32.53
GROUP 2$61.70$32.53
GROUP 3$60.37$32.53
GROUP 4$59.23$32.53
GROUP 5$58.09$32.53
IRONWORKER$43.75$34.45
IRONWORKER$50.70$35.15
LABORER (ASBESTOS/MOLD/LEAD LABORER) Marin and Napa Counties$37.75$29.69
Remaining Counties$36.75$29.69
LABORER (TRAFFIC CONTROL/LANE CLOSURE) Escort Driver, Flag Person Area A$37.26$27.32
Area B$36.26$27.32
Traffic Control Person I Area A$37.56$27.32
Area B$36.56$27.32
Traffic Control Person II Area A$35.06$27.32
Area B$34.06$27.32
LABORER Mason Tender-Brick$36.29$25.55
Tunnel and Shaft Laborers: GROUP 1$45.89$27.72
GROUP 2$45.66$27.72
GROUP 3$45.41$27.72
GROUP 4$44.96$27.72
GROUP 5$44.42$27.72
Shotcrete Specialist$46.41$27.72
LABORER (CONSTRUCTION CRAFT LABORERS - AREA B:) Construction Specialist Group$36.20$27.30
GROUP 1$35.50$27.30
GROUP 1-a$35.72$27.30
GROUP 1-c$35.55$27.30
GROUP 1-e$36.05$27.30
GROUP 1-f$30.37$23.20
GROUP 2$35.35$27.30
GROUP 3$35.25$27.30
GROUP 4$28.94$27.30
See groups 1-b and 1-d under laborer classifications. LABORER (GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA B:) (1) New Construction$35.25$27.30
Establishment Warranty Period$28.94$27.30
LABORER (GUNITE - AREA B:) GROUP 1$36.46$27.30
GROUP 2$35.96$27.30
GROUP 3$35.37$27.30
GROUP 4$35.25$27.30
LABORER (WRECKING - AREA B:) GROUP 1$35.50$27.30
Plasterer tender$39.77$28.54
LABORER (TRAFFIC CONTROL/LANE CLOSURE) Escort Driver, Flag Person$37.26$27.30
Traffic Control Person I$37.56$27.30
Traffic Control Person II$35.06$27.30
LABORER Mason Tender-Brick$37.54$25.55
LABORER (CONSTRUCTION CRAFT LABORERS - AREA A:) Construction Specialist Group$37.20$27.30
GROUP 1$36.50$27.30
GROUP 1-a$36.72$27.30
GROUP 1-c$36.55$27.30
GROUP 1-e$37.05$27.30
GROUP 1-f$31.37$23.20
GROUP 2$36.35$27.30
GROUP 3$36.25$27.30
GROUP 4$29.94$27.30
See groups 1-b and 1-d under laborer classifications. LABORER (GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA A:) (1) New Construction$36.25$27.30
Establishment Warranty Period$29.94$27.30
LABORER (GUNITE - AREA A:) GROUP 1$37.46$27.30
GROUP 2$36.96$27.30
GROUP 3$36.37$27.30
GROUP 4$36.25$27.30
LABORER (WRECKING - AREA A:) GROUP 1$36.50$27.30
LABORER (TRAFFIC CONTROL/LANE CLOSURE) Escort Driver, Flag Person$36.26$27.30
Traffic Control Person I$36.56$27.30
Traffic Control Person II$34.06$27.30
LABORER Mason Tender-Brick$36.84$26.24
GROUP 1-f$36.08$27.30
Painters$53.38$28.04
DRYWALL FINISHER/TAPER$59.63$31.29
Painters$43.45$22.80
SOFT FLOOR LAYER$59.00$33.03
GLAZIER$56.22$34.00
Painters: Brush and Roller$39.43$16.16
Paperhanger$42.19$16.16
Spray Painter$41.43$16.16
SOFT FLOOR LAYER$34.27$16.47
Drywall (1) Taper$42.79$16.12
Steeplejack - Taper, over 40 ft with open space below$44.29$16.12
GLAZIER$43.25$35.62
Parking Lot Striping/Highway Marking: GROUP 1$40.83$17.62
GROUP 2$34.71$17.62
GROUP 3$35.11$17.62
SOFT FLOOR LAYER$48.54$26.59
s PLASTERER AREA 295: Alpine, Amador, Butte, Colusa, El Dorado, Glenn, Lassen, Modoc, Nevada, Placer, Plumas, Sacramento, Shasta, Sierra, Siskiyou, Solano, Sutter, Tehema, Trinity, Yolo & Yuba Counties$32.70$31.68
AREA 355: Marin$36.73$31.68
AREA 355: Napa & Sonoma Counties$32.70$31.68
CEMENT MASON/CONCRETE FINISHER$32.15$23.27
rcial work such as hospitals, prisons, hotels, schools, casinos, wastewater treatment plants, and resarch facilities as well as refrigeration pipefitting, service and repair work - MARKET RECOVERY RATE$69.70$46.38
All other work - NEW CONSTRUCTION RATE$91.00$49.40
Landscape/Irrigation Fitter (Underground/Utility Fitter)$77.35$36.53
PLUMBER$52.75$41.39
PLUMBER/PIPEFITTER Light Commercial$30.85$20.40
All Other Work$71.60$38.38
PLUMBER/PIPEFITTER$52.14$18.71
Underground Utility Worker /Landscape Fitter$36.01$18.50
PLUMBER$58.45$38.74
PLUMBER/PIPEFITTER Journeyman$67.37$30.00
Light Commercial Work$55.58$24.02
Roofer$54.94$23.34
Roofer$46.73$21.36
SPRINKLER FITTER (Fire Sprinklers)$81.54$41.35
SPRINKLER FITTER$52.06$29.86
or less$55.92$45.29
All other work$64.06$46.83