Davis-Bacon
CA20260001 (Rev 3)
Coverage: California • San Diego.
Published: May 18, 2026
Status: Active
Standard: Yes
Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| ASBESTOS WORKERS/INSULATOR (INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS, AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS) | $56.32 | $26.52 |
| FIRE STOP TECHNICIAN (APPLICATION OF FIRESTOPPING MATERIALS FOR WALL OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND CURTAIN WALLS) | $39.94 | $20.65 |
| TERIAL HANDLER (INCLUDES PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS FROM MECHANICAL SYSTEMS, WHETHER THEY CONTAIN ASBESTOS OR NOT) | $23.52 | $13.37 |
| BOILERMAKER | $51.98 | $42.11 |
| BRICKLAYER; MARBLE SETTER | $46.73 | $19.02 |
| TILE LAYER | $51.82 | $19.32 |
| TILE FINISHER | $37.96 | $13.77 |
| MARBLE FINISHER | $43.38 | $15.36 |
| TERRAZZO WORKER/SETTER | $49.62 | $15.26 |
| TERRAZZO FINISHER | $42.11 | $14.67 |
| DRYWALL: DRYWALL STOCKER/SCRAPPER ((1) WORK ON WOOD FRAMED CONSTRUCTION OF SINGLE FAMILY RESIDENCES, APARTMENTS OR CONDOMINIUMS UNDER FOUR STORIES) | $22.16 | $8.62 |
| DRYWALL: DRYWALL INSTALLER/LATHER ((1) WORK ON WOOD FRAMED CONSTRUCTION OF SINGLE FAMILY RESIDENCES, APARTMENTS OR CONDOMINIUMS UNDER FOUR STORIES) | $32.14 | $16.28 |
| DRYWALL: DRYWALL STOCKER/SCRAPPER (2) ALL OTHER WORK | $21.45 | $12.18 |
| DRYWALL: DRYWALL INSTALLER/LATHER (2) ALL OTHER WORK | $44.53 | $27.09 |
| PILEDRIVERMAN | $52.37 | $26.18 |
| CARPENTER: (5) RESIDENTIAL INSULATION INSTALLER | $24.16 | $15.76 |
| CARPENTER: (4) RESIDENTIAL CARPENTER | $39.15 | $26.18 |
| CARPENTER: (3) HEAVY & HIGHWAY | $51.40 | $16.28 |
| CARPENTER: (2) COMMERCIAL BUILDING | $48.94 | $26.18 |
| CARPENTER: (1) BRIDGE | $52.37 | $26.18 |
| RATES' COLUMN ARE PER DAY | $418.96 | $26.18 |
| RATES' COLUMN ARE PER DAY | $442.96 | $26.18 |
| RATES' COLUMN ARE PER DAY | $450.96 | $26.18 |
| RATES' COLUMN ARE PER DAY | $901.92 | $26.18 |
| MODULAR FURNITURE INSTALLER | $25.00 | $13.06 |
| MILLWRIGHT | $52.24 | $26.68 |
| ELECTRICIAN: (ALL OTHER WORK, INCLUDING 4 STORIES RESIDENTIAL) | $58.95 | $18.85 |
| ELECTRICIAN: (TUNNEL WORK) CABLE SPLICER | $67.16 | $19.09 |
| ELECTRICIAN: (ALL OTHER WORK, INCLUDING 4 STORIES RESIDENTIAL) CABLE SPLICER | $59.70 | $18.87 |
| ELECTRICIAN: (TUNNEL WORK) | $66.32 | $19.07 |
| UND, IMPULSES AND VIDEO. EXCLUDED FROM THIS SCOPE OF WORK - TRANSMISSION, SERVICE AND MAINTENANCE OF BACKGROUND MUSIC. ALL OF THE ABOVE SHALL INCLUDE THE INSTALLATION AND TRANSMISSION OVER FIBER OPTICS | $43.78 | $15.39 |
| BSITE, INSTALLATION OF UNDERGROUND DUCTS FOR ELECTRICAL, TELEPHONE, CABLE TV LAND COMMUNICATION SYSTEMS. THE SETTING, LEVELING, GROUNDING AND RACKING OF PRECAST MANHOLES, HANDHOLES AND TRANSFORMER PADS | $33.10 | $14.09 |
| IN DUCTS. THE LAYOUT OF ELECTRICAL SYSTEMS AND COMMUNICATION INSTALLATION INCLUDING PROPER POSITION OF TRENCH DEPTHS, AND RADIUS AT DUCT BANKS, LOCATION FOR MANHOLES, STREET LIGHTS AND TRAFFIC SIGNALS | $43.62 | $14.41 |
| ELECTRICIAN (RESIDENTIAL, 1-3 STORIES) | $40.50 | $8.18 |
| tes Fringes LINE CONSTRUCTION: (4) POWDERMAN HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DAY AFTER THANKSGIVING, CHRISTMAS DAY | $51.87 | $18.79 |
| LINE CONSTRUCTION: (3) GROUNDMAN HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DAY AFTER THANKSGIVING, CHRISTMAS DAY | $40.76 | $21.76 |
| D & UNDERGROUND DISTRIBUTION LINE EQUIPMENT) HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DAY AFTER THANKSGIVING, CHRISTMAS DAY | $53.30 | $22.26 |
| INE CONSTRUCTION: (1) LINEMAN; CABLE SPLICER HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DAY AFTER THANKSGIVING, CHRISTMAS DAY | $70.16 | $24.71 |
| FOR 6 MONTHS TO 5 YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS' DAY, THANKSGIVING DAY, FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY | $69.43 | $38.44 |
| OPERATOR: POWER EQUIPMENT: (6) BARGE MATE (DREDGING) | $61.34 | $40.95 |
| OPERATOR: POWER EQUIPMENT: (5) FIREMAN-OILER, DECKHAND, BARGEMAN, LEVEEHAND (DREDGING) | $60.73 | $40.95 |
| OPERATOR: POWER EQUIPMENT: (4) WINCH OPERATOR (STERN WINCH ON DREDGE) (DREDGING) | $61.27 | $40.95 |
| OPERATOR: POWER EQUIPMENT: (3) DECKMATE (DREDGING) | $61.82 | $40.95 |
| OPERATOR: POWER EQUIPMENT: (2) DREDGE DOZER (DREDGING) | $61.93 | $40.95 |
| OPERATOR: POWER EQUIPMENT: (1) LEVERMAN (DREDGING) | $67.90 | $40.95 |
| per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator | $66.91 | $33.20 |
| per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator | $66.79 | $33.20 |
| per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator | $66.68 | $33.20 |
| per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator | $66.46 | $33.20 |
| per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator | $66.32 | $33.20 |
| per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator | $66.03 | $33.20 |
| per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator | $65.25 | $33.20 |
| operator (over 300 tons); Derrick barge operator (over 300 tons); Helicopter pilot; Hoist operator, stiff legs, Guy derrick or similar type (over 300 tons); Mobile tower crane operator (over 300 tons) | $70.75 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $69.75 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $68.75 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $67.75 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $66.75 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $66.58 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $66.41 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $66.29 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $66.18 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $65.96 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $65.82 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $65.53 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $64.75 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $67.91 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $67.79 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $67.68 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $67.58 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $67.41 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $67.29 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $67.18 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $67.08 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $66.71 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $64.67 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $64.18 | $33.20 |
| PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | $63.40 | $33.20 |
| additional per hour at the following locations: Port Hueneme, Port Mugu, U.S. Coast Guard Station - Two Rock | $50.70 | $35.15 |
| additional per hour at the following locations: Port Hueneme, Port Mugu, U.S. Coast Guard Station - Two Rock | $45.78 | $26.51 |
| PLACING; DRILLER-ALL POWER DRILLS, EXCLUDING JACKHAMMER, WHETHER CORE, DIAMOND, WAGON, TRACK, MULTIPLE UNIT, AND ANY AND ALL OTHER TYPES OF MECHANICAL DRILLS WITHOUT REGARD TO THE FORM OF MOTIVE POWER | $48.16 | $25.09 |
| TO THE NATURE OF MATERIAL FROM WHICH THE TUBULAR MATERIAL IS FABRICATED; NO JOINT PIPE AND STRIPPING OF SAME; PREFABRICATED MANHOLE INSTALLER; SANDBLASTER (NOZZLEMAN), PORTA SHOT-BLAST, WATER BLASTING | $48.64 | $25.09 |
| LL OTHER SERVICES; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCAARIFIER; STEEL HEADER BOARD MAN AND GUIDELINE SETTER; TAMPERS, BARKO, WACKER AND SIMILAR TYPE; TRENCHING MACHINE, HANDPROPELLED | $47.16 | $25.09 |
| NCRETE; ROTO SCRAPER AND TILLER; TANK SEALER AND CLEANER; TREE CLIMBER, FALLER, CHAIN SAW OPERATOR, PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; UNDERGROUND LABORERS, INCLUDING CAISSON BELLOWER | $46.30 | $25.09 |
| EGEE MAN, SHUTTLE MAN, TOP MAN), FILLING OF CRACKS BY ANY METHOD ON ANY SURFACE; TARMAN AND MORTAR MAN; TOOL CRIB OR TOOL HOUSE LABORER; WINDOW CLEANER; WIRE MESH PULING-ALL CONCRETE POURING OPERATIONS | $45.54 | $25.09 |
| UTILITIES AND (C) ANY FINE GRADING WORK, UTILITY WORK OR PAVING WORK IN THE FUTURE STREET AND PUBLIC RIGHT-OF-WAY; BUT INCLUDING ALL ROUGH GRADING WORK AT THE JOB SITE BEHIND THE EXISTING RIGHT OF WAY | $43.44 | $23.42 |
| UTILITIES AND (C) ANY FINE GRADING WORK, UTILITY WORK OR PAVING WORK IN THE FUTURE STREET AND PUBLIC RIGHT-OF-WAY; BUT INCLUDING ALL ROUGH GRADING WORK AT THE JOB SITE BEHIND THE EXISTING RIGHT OF WAY | $42.15 | $23.42 |
| LABORER: MASON TENDER | $42.60 | $22.13 |
| ECHANICAL DRILLS WITHOUT REGARD TO FORM OF MOTIVE POWER. ENVIRONMENTAL REMEDIATION, MONITORING WELL, TOXIC WASTE AND GEOTECHNICAL DRILLER, TOXIC WASTE REMOVAL. WELDING IN CONNECTION WITH LABORER'S WORK | $50.14 | $25.09 |
| ER DISTRIBUTOR BOOTMAN; OVERSIZE CONCRETE VIBRATOR OPERATORS, 70 POUNDS OR OVER. PIPELAYER, PRFEFABRICATED MANHOLE INSTALLER, SANDBLAST NOZZLEMAN (WATER BALSTING-PORTA SHOT BLAST), TRAFFIC LANE CLOSURE | $49.28 | $25.09 |
| CONCRETE CHIPPER SCARIFIER), ROCK SLINGER, SHOT BLAST EQUIPMENT (8 TO 48 INCHES), STEEL HEADERBOARD MAN AND GUIDELINE SETTER, TAMPER/WACKER OPERATOR AND SIMILAR TYPES, TRENCHING MACHINE HAND PROPELLED | $47.76 | $25.09 |
| OT TENDER; SEPTIC TANK DIGGER/INSTALLER; TAMPER/WACKER OPERATOR; TANK SCALER & CLEANER; TAR MAN & MORTAR MAN; TREE CLIMBER/FALLER, CHAINB SAW OPERATOR, PITTSBURGH CHIPPER & SIMILAR TYPE BRUSH SHREDDERS | $47.20 | $25.09 |
| DS; RIGGING & SIGNALING; SCALER, SLIP-FORM RAISERS, FILLING CRACKS ON ANY SURFACE, TOOL CRIB OR TOOL HOUSE LABORER, TRAFFIC CONTROL (SIGNS, BARRIERS, BARRICADES, DELINEATOR, CONES ETC.), WINDOW CLEANER | $46.66 | $25.09 |
| URE AND DISPOSAL OF ASBESTOS- CONTAINING MATERIALS AND TOXIC WASTE BY HAND OR WITH EQUIPMENT OR MACHINERY; SCAFFOLDING, FABRICATION OF TEMPORARY WOODEN BARRIERS AND ASSEMBLY OF DECONTAMINATION STATIONS | $46.48 | $25.93 |
| LEVEL SHALL BE COMPENSATED FOR AT 35 CENTS PER HOUR ABOVE THE APPLICABLE CLASSIFICATION WAGE RATE | $51.39 | $23.77 |
| LEVEL SHALL BE COMPENSATED FOR AT 35 CENTS PER HOUR ABOVE THE APPLICABLE CLASSIFICATION WAGE RATE | $54.93 | $23.77 |
| LEVEL SHALL BE COMPENSATED FOR AT 35 CENTS PER HOUR ABOVE THE APPLICABLE CLASSIFICATION WAGE RATE | $55.88 | $23.77 |
| OUP 4 STRIPER: LAYOUT AND APPLICATION OF TRAFFIC STRIPES AND MARKINGS; HOT THERMO PLASTIC; TAPE TRAFFIC STRIPES AND MARKINGS, INCLUDING TRAFFIC CONTROL; OPERATION OF ALL RELATED MACHINERY AND EQUIPMENT | $54.35 | $23.97 |
| MANENTLY AFFIXED ROADSIDE AND PARKING DELINEATION BARRICADES, FENCING, CABLE ANCHOR, GUARD RAIL, REFERENCE SIGNS, MONUMENT MARKERS; OPERATION OF ALL RELATED MACHINERY AND EQUIPMENT; POWER BROOM SWEEPER | $52.61 | $23.97 |
| AND PREPARATION OF SURFACE FOR COATINGS. TRAFFIC CONTROL PERSON: CONTROLLING AND DIRECTING TRAFFIC THROUGH BOTH CONVENTIONAL AND MOVING LANE CLOSURES; OPERATION OF ALL RELATED MACHINERY AND EQUIPMENT | $50.60 | $23.97 |
| INCLUDING REPAIR AND FILLING OF CRACKS BY ANY METHOD ON ANY SURFACE IN PARKING LOTS, GAME COURTS AND PLAYGROUNDS; CARSTOPS; OPERATION OF ALL RELATED MACHINERY AND EQUIPMENT; EQUIPMENT REPAIR TECHNICIAN | $49.30 | $23.97 |
| LABORERS: HORIZONTAL DIRECTIONAL DRILLING: (4) ELECTRONIC TRACKING LOCATOR | $51.96 | $20.86 |
| LABORERS: HORIZONTAL DIRECTIONAL DRILLING: (3) HORIZONTAL DIRECTIONAL DRILL OPERATOR | $49.96 | $20.86 |
| LABORERS: HORIZONTAL DIRECTIONAL DRILLING: (2) VEHICLE OPERATOR/HAULER | $48.11 | $20.86 |
| LABORERS: HORIZONTAL DIRECTIONAL DRILLING: (1) DRILLING CREW LABORER | $47.94 | $20.86 |
| IAL BEACH NAVAL AIR STATION, MARINE CORPS LOGISTICS SUPPLY BASE, MARINE CORPS PICKLE MEADOWS, MOUNTAIN WARFARE TRAINING CENTER, NAVAL AIR FACILITY-SEELEY, NORTH ISLAND NAVAL AIR STATION, VANDENBERG AFB | $48.72 | $25.97 |
| IAL BEACH NAVAL AIR STATION, MARINE CORPS LOGISTICS SUPPLY BASE, MARINE CORPS PICKLE MEADOWS, MOUNTAIN WARFARE TRAINING CENTER, NAVAL AIR FACILITY-SEELEY, NORTH ISLAND NAVAL AIR STATION, VANDENBERG AFB | $46.17 | $25.97 |
| PAINTERS: INCLUDING LEAD ABATEMENT: (2) ALL OTHER WORK | $38.52 | $18.64 |
| DRYWALL FINISHER/TAPER (1) BUILDING & HEAVY CONSTRUCTION | $43.59 | $24.80 |
| DRYWALL FINISHER/TAPER (2) Residential Construction (Wood frame apartments, single family homes and multi-duplexes up to and including four stories) | $32.27 | $14.70 |
| GLAZIER | $52.90 | $22.16 |
| SOFT FLOOR LAYER | $40.77 | $19.37 |
| ADDITIONAL PER HOUR | $47.37 | $19.64 |
| CEMENT MASON/CONCRETE FINISHER GROUP 3: ALL OTHER WORK | $30.07 | $21.12 |
| CEMENT MASON/CONCRETE FINISHER GROUP 2: Work classified as type I and II construction | $27.99 | $19.77 |
| od frame project of any size; work classified as Type III, IV or Type V construction; interior tenant improvement work regardless the size of the project; any wood frame project of four stories or less | $26.34 | $19.77 |
| PLUMBER, PIPEFITTER, STEAMFITTER: WORK ONLY ON STRIP MALLS, LIGHT COMMERCIAL, TENANT IMPROVEMENT AND REMODEL WORK | $44.29 | $24.16 |
| W ADDITIONS AND REMODELING OF BARS, RESTAURANT, STORES AND COMMERCIAL BUILDINGS NOT TO EXCEED 5,000 SQ. FT. OF FLOOR SPACE AND WORK ON STRIP MALLS, LIGHT COMMERCIAL, TENANT IMPROVEMENT AND REMODEL WORK | $61.73 | $26.81 |
| PLUMBER, PIPEFITTER, STEAMFITTER: WORK ONLY ON NEW ADDITIONS AND REMODELING OF COMMERCIAL BUILDINGS, BARS, RESTAURANTS, AND STORES NOT TO EXCEED 5,000 SQ. FT. OF FLOOR SPACE | $59.85 | $25.83 |
| PLUMBER, PIPEFITTER, STEAMFITTER: CAMP PENDLETON; VANDENBERG AIR FORCE BASE | $66.23 | $26.81 |
| PLUMBER/PIPEFITTER (RESIDENTIAL) | $48.83 | $22.73 |
| PLUMBER (SEWER & STORM DRAIN WORK) | $48.84 | $23.58 |
| PLUMBER (LANDSCAPE/IRRIGATION FITTER) | $44.75 | $26.20 |
| ROOFER | $42.80 | $12.64 |
| SPRINKLER FITTER | $52.53 | $28.19 |
| e. TENANT IMPROVEMENT WORK: Any work necessary to finish interior spaces to conform to the occupants of commercial buildings, after completion of the building shell | $38.65 | $10.31 |
| SHEET METAL WORKER (EXCEPT CAMP PENDLETON) | $51.45 | $30.92 |
| SHEET METAL WORKER (CAMP PENDLETON) | $53.45 | $30.92 |
| PER HOUR. WORKERS SHALL BE PAID HAZMAT PAY IN INCREMENTS OF FOUR (4) AND EIGHT (8) HOURS | $45.31 | $27.07 |
| PER HOUR. WORKERS SHALL BE PAID HAZMAT PAY IN INCREMENTS OF FOUR (4) AND EIGHT (8) HOURS | $43.80 | $27.07 |
| PER HOUR. WORKERS SHALL BE PAID HAZMAT PAY IN INCREMENTS OF FOUR (4) AND EIGHT (8) HOURS | $43.31 | $27.07 |
| PER HOUR. WORKERS SHALL BE PAID HAZMAT PAY IN INCREMENTS OF FOUR (4) AND EIGHT (8) HOURS | $43.11 | $27.07 |
| PER HOUR. WORKERS SHALL BE PAID HAZMAT PAY IN INCREMENTS OF FOUR (4) AND EIGHT (8) HOURS | $42.91 | $27.07 |
| PER HOUR. WORKERS SHALL BE PAID HAZMAT PAY IN INCREMENTS OF FOUR (4) AND EIGHT (8) HOURS | $42.71 | $27.07 |
| PER HOUR. WORKERS SHALL BE PAID HAZMAT PAY IN INCREMENTS OF FOUR (4) AND EIGHT (8) HOURS | $32.12 | $27.07 |
Related Wage Determinations
View directory →Davis-Bacon
CA20260009 (Rev 1)
California • Fresno, Kern, Madera +4
Davis-Bacon
CA20260026 (Rev 3)
California • San Bernardino
Davis-Bacon
CA20260002 (Rev 3)
California • Imperial
Davis-Bacon
CA20260016 (Rev 3)
California • Tulare
Davis-Bacon
CA20260015 (Rev 3)
California • Ventura
Davis-Bacon
CA20260017 (Rev 3)
California • Imperial, Los Angeles, Orange +5