OccupationBaseFringe
ASBESTOS WORKER/HEAT & FROST INSULATOR (MECHANICAL- DUCT, PIPE & MECHANICAL SYSTEM INSULATION)$39.18$26.07
BOILERMAKER$55.00$35.48
MASON - STONE$32.66$21.58
BRICKLAYER (INCLUDING POINTING, CAULKING, AND CLEANING)$32.66$21.58
TILE FINISHER$27.63$13.94
TILE SETTER$32.85$17.56
CARPENTER (ACOUSTICAL CEILING INSTALLER ONLY)$36.84$20.19
CARPENTER (INCLUDING DRYWALL HANGING, METAL STUD INSTALLATION, FORM WORK AND SCAFFOLD BUILDING)$36.84$20.19
MILLWRIGHT$43.00$23.44
ELECTRICIAN (ALARM INSTALLATION, HVAC/TEMPERATURE CONTROLS INSTALLATION AND LOW VOLTAGE WIRING ONLY)$41.00$31.06
DAYS BEFORE AND THE WORKING DAY AFTER THE HOLIDAY): NEW YEARS'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERAN'S DAY; THANKSGIVING DAY AND THE FRIDAY AFTER THANKSGIVING DAY, AND CHRISTMAS DAY$61.41$38.44
POWER EQUIPMENT OPERATOR (PUMP)$28.36$18.10
POWER EQUIPMENT OPERATOR (6) OILER$39.42$29.30
POWER EQUIPMENT OPERATOR (4) PUMP$40.74$29.70
POWER EQUIPMENT OPERATOR (3) HOIST (SINGLE DRUM), FORKLIFT (UNDER 20 FT)$41.88$30.03
POWER EQUIPMENT OPERATOR (2) BOBCAT/ SKID/ STEER/ SKID LOADER, BULLDOZER, HOIST (WITH TWO TOWERS), MECHANIC, LOADER, FORKLIFT (20 FT. AND OVER)$44.61$30.83
POWER EQUIPMENT OPERATOR (1A) CRANE$47.14$31.58
IRONWORKER (ORNAMENTAL, STRUCTURAL, & REINFORCING)$37.26$32.63
LABORER: COMMON OR GENERAL$21.02$16.88
LABORER (MASON TENDER- BRICK)$23.41$11.19
LABORER (FORKLIFT (MASONRY WORK ONLY))$24.91$11.19
LABORER (CONCRETE WORKER; CONCRETE SAW (WALK BEHIND/HAND HELD))$20.07$11.19
PAINTER (BRUSH, ROLLER, SPRAY, AND DRYWALL FINISHING/TAPING)$27.95$16.12
PLUMBER$41.36$29.45
PIPEFITTER (INCLUDES HVAC PIPE AND HVAC UNIT INSTALLATION)$41.36$29.45
ROOFER (EXCLUDES WATERPROOFING)$40.33$32.62
SPRINKLER FITTER (FIRE SPRINKLERS)$49.75$28.96
SHEET METAL WORKER (INCLUDES HVAC DUCT AND SIDING INSTALLATION - METAL/ALUMINUM/VINYL)$36.13$30.32
TRUCK DRIVER: DUMP TRUCK$23.36$7.60
ROOFER: WATERPROOFING ONLY$28.60$18.02
OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE)$33.01$18.37
OPERATOR: GRADER/BLADE$32.51$17.98
OPERATOR: GRADALL$32.70$18.43
OPERATOR: DRILL$28.55$15.78
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$30.73$15.10
LABORER: MASON TENDER - CEMENT/CONCRETE$27.89$19.81
CEMENT MASON/CONCRETE FINISHER$32.66$21.32