Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $43.88 | $26.93 |
| BRICKLAYER | $36.53 | $24.03 |
| BRICK POINTER/CAULKER/CLEANER | $36.53 | $24.03 |
| TILE SETTER | $36.53 | $24.03 |
| TILE FINISHER | $30.78 | $23.04 |
| CARPENTER (Excluding Drywall Hanging and Metal Stud Installation, Soft Floor Laying, and Form Work) | $34.42 | $26.53 |
| SOFT FLOOR LAYER | $37.52 | $23.50 |
| CARPENTER (Drywall Hanging and Metal Stud Installation Only) | $37.52 | $23.50 |
| PILEDRIVERMAN | $36.34 | $27.50 |
| ELECTRICIAN (Low Voltage Wiring Only) | $33.05 | $14.91 |
| ELECTRICIAN (Including HVAC/Temperature Controls and Alarm Installation) | $46.63 | $24.92 |
| ELECTRICIAN (Excludes Low Voltage Wiring and Installation of Alarms/HVAC Temperature Controls) | $42.95 | $18.81 |
| ELEVATOR MECHANIC | $63.79 | $38.43 |
| POWER EQUIPMENT OPERATOR Crane | $46.71 | $16.41 |
| Oiler | $36.93 | $16.41 |
| POWER EQUIPMENT OPERATOR Forklift | $28.87 | $19.66 |
| Grader/Blade | $32.42 | $19.66 |
| Mechanic | $32.92 | $19.66 |
| IRONWORKER Ornamental, Reinforcing, & Structural | $36.83 | $29.01 |
| LABORER Mason Tender - Brick & Cement/Concrete | $31.89 | $22.66 |
| LABORER Common or General | $32.35 | $16.42 |
| LABORER Pipelayer | $31.27 | $10.90 |
| GLAZIER | $34.82 | $20.80 |
| PAINTER (Brush and Roller) | $32.35 | $19.45 |
| PAINTER (Drywall Finishing/Taping Only) | $35.45 | $20.20 |
| PLASTERER (Including FLOOR LAYER: Floor Coating/Epoxy) | $29.51 | $15.67 |
| CEMENT MASON/CONCRETE FINISHER | $35.73 | $24.65 |
| PLUMBER (Excludes HVAC Pipe Installation) | $44.86 | $30.03 |
| PIPEFITTER (Includes HVAC Pipe Installation) | $49.17 | $28.55 |
| SPRINKLER FITTER (Fire Sprinklers) | $49.17 | $28.55 |
| ROOFER | $29.07 | $19.84 |
| SHEET METAL WORKER (HVAC Duct and Unit Installation Only) | $43.06 | $30.11 |
| CARPENTER (Form Work Only) | $31.87 | $12.74 |
| LABORER: Asphalt, Includes Raker, Shoveler, Spreader and Distributor | $24.53 | $14.55 |
| OPERATOR: Backhoe/Excavator/Trackhoe | $30.95 | $10.20 |
| OPERATOR: Bobcat/Skid Steer/Skid Loader | $32.88 | $12.26 |
| OPERATOR: Bulldozer | $21.15 | $8.72 |
| OPERATOR: Loader | $29.66 | $12.61 |
| OPERATOR: Paver (Asphalt, Aggregate, and Concrete) | $31.48 | $12.80 |
| OPERATOR: Roller | $31.48 | $12.80 |
| PAINTER: Spray | $22.78 | $12.40 |
| SHEET METAL WORKER, Excludes HVAC Duct and Unit Installation | $26.88 | $15.95 |
| TRUCK DRIVER: Dump (All Types) | $24.32 | $11.73 |