Skip to content
Davis-Bacon

OH20260034 (Rev 0)

Coverage: Ohio • Auglaize.

Published: Jan 02, 2026
Status: Active
Standard: Yes

Occupation Rates

Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.

OccupationBaseFringe
ASBESTOS WORKER/HEAT & FROST INSULATOR$37.00$28.27
BRICK POINTER/CAULKER/CLEANER$33.30$18.28
SOFT FLOOR LAYER$30.25$25.16
POWER EQUIPMENT OPERATOR Crane; Scraper$44.14$16.41
Forklift$42.98$16.41
IRONWORKER, STRUCTURAL$35.50$29.20
IRONWORKER, ORNAMENTAL$36.00$23.57
LABORER Chain Link/Cyclone Fence Erection$28.73$11.80
LABORER Mason Tender - Cement/Concrete$32.35$16.42
GLAZIER$36.50$25.06
PIPEFITTER (Excludes HVAC Pipe Installation)$51.00$32.56
PLUMBER (HVAC Pipe Installation Only)$51.00$32.56
ROOFER$29.07$19.84
SHEET METAL WORKER (Excludes HVAC Duct and Unit Installation)$39.58$35.15
BRICKLAYER: TILE FINISHER$26.88$11.81
BRICKLAYER: TILE SETTER$29.90$16.52
IRONWORKER, REINFORCING$33.18$23.73
BRICKLAYER$27.47$12.26
CARPENTER (Excluding Soft Floor Laying)$21.09$9.08
CEMENT MASON/CONCRETE FINISHER$23.47$10.07
DRYWALL FINISHER/TAPER$18.57$3.12
DRYWALL HANGER AND METAL STUD INSTALLER$17.63$5.64
LABORER: Common or General$18.22$8.60
LABORER: Landscape & Irrigation$10.39$0.00
LABORER: Mason Tender - Brick$22.74$8.60
LABORER: Pipelayer$18.37$4.79
OPERATOR: Backhoe/Excavator/Trackhoe$20.00$2.90
OPERATOR: Bobcat/Skid Steer/Skid Loader$20.00$3.26
OPERATOR: Bulldozer$23.50$7.51
OPERATOR: Loader$17.43$2.72
OPERATOR: Paver (Asphalt, Aggregate, and Concrete)$25.85$10.42
PAINTER (Brush and Roller)$17.91$10.85
PLUMBER, Excludes HVAC Pipe Installation$29.57$17.20
SHEET METAL WORKER (HVAC Duct and HVAC Unit Installation Only)$21.31$4.39
SPRINKLER FITTER (Fire Sprinklers)$25.91$9.18
TRUCK DRIVER: Dump (All Types)$14.97$2.01

Related Wage Determinations