OccupationBaseFringe
Asbestos Worker/Heat and Frost Insulator$40.77$20.17
HAZARDOUS MATERIAL HANDLER$24.46$10.19
Fire Stop Technician$30.21$10.43
Boilermakers$47.37$25.60
Bricklayer$38.80$15.17
BRICKLAYER Refractory (Firebrick)$43.94$17.74
Carpenter/Lather$34.41$14.33
MILLWRIGHT$39.50$17.32
PILEDRIVERMAN$36.60$14.47
DIVER TENDER$36.60$14.47
DIVER$43.92$14.47
Electricians$59.50$23.06
Power equipment operators: (HEAVY AND HIGHWAY CONSTRUCTION) GROUP 1$45.76$13.27
a GROUP 2$43.44$13.27
a GROUP 3$40.73$13.27
a GROUP 4$36.31$13.27
a GROUP 5$31.09$13.27
a GROUP 6$28.39$13.27
a GROUP 7$47.18$13.27
Power equipment operators: (PAVING AND INCIDENTAL GRADING) GROUP 1$37.07$11.17
GROUP 2$32.89$11.17
GROUP 3$28.09$11.17
GROUP 4$25.14$11.17
GROUP 5$37.93$10.97
Power equipment operators: (SEWER, GAS AND WATER LINE CONSTRUCTION) GROUP 1$41.40$11.55
a GROUP 2$35.00$11.55
a GROUP 3$33.80$11.55
a GROUP 4$33.26$11.55
a GROUP 5$31.16$11.55
a GROUP 6$25.89$11.55
IRONWORKER, STRUCTURAL AND ORNAMENTAL$37.86$25.86
IRONWORKER, REINFORCING$31.88$23.78
Laborers: (HEAVY AND HIGHWAY AND SEWER & WATER LINES CONSTRUCTION) GROUP 1$33.25$8.70
GROUP 2$34.27$8.70
GROUP 3$34.27$8.70
GROUP 4$34.32$8.70
GROUP 5$35.00$8.70
GROUP 6$35.93$8.70
GROUP 7$36.81$8.70
GROUP 8$37.95$8.70
ges Laborers: (HAZARDOUS WASTE REMOVAL, EXCEPT ON MECHANICAL SYSTEMS: Preparation for, removing and encapsulation of hazardous materials from non-mechanical systems) Skilled Asbestos Abatement Laborers$32.25$8.70
Skilled Toxic and Hazardous Waste Removal Laborers$32.25$8.70
Laborers: (TUNNEL, RAISE & SHAFT (FREE AIR) FOR HEAVY AND SEWER & WATER LINES CONSTRUCTION) GROUP 1$34.41$8.70
GROUP 2$35.48$8.70
GROUP 3$38.17$8.70
GROUP 4$39.29$8.70
Laborers: (TUNNEL, RAISE AND SHAFT (COMPRESSED AIR) FOR HEAVY CONSTRUCTION ONLY Gauge Pressure Work Period (Pounds) (Hours) 1-14 7$44.04$8.70
Laborers: (PAVING AND INCIDENTAL GRADING) Asphalt Raker & Concrete Saw Operator$24.30$8.74
Asphalt Shoveler$23.27$8.74
Asphalt Tamper & Concrete Shoveler$23.86$8.74
Jack Hammer$23.89$8.74
Laborer$23.06$8.74
Sand Setter & Form Setter$25.10$8.74
LABORERS (BRICK MASONRY WORK) Mason Tenders$24.31$8.70
Scaffold Builders, Mortarmen$24.96$8.70
Marble & Stone Mason Includes Pointing, Caulking and Cleaning of All Types of Masonry, Brick, Stone and Cement Structures$45.65$21.21
Mosaic & Terrazzo Worker, Tile Layer$34.34$14.20
Marble, Tile & Terrazzo Finisher$28.85$12.55
Painters: All Industrial Work$34.30$12.98
Bridges, Heavy Highway, Lead Abatement and Flame/Thermal Spray$42.93$13.77
Commercial and Mold Remediation, Painters, Wallcovers and Drywall Finishers$29.16$11.86
Metal Polishing and Refinishing$28.46$11.56
Cement Masons: HEAVY CONSTRUCTION ONLY$30.50$14.23
Cement Masons: (PAVING & INCIDENTAL GRADING) Cement Masons$23.50$9.75
Concrete Saw Operators$23.50$9.75
Form Setters$23.50$9.75
Plumbers$53.30$23.71
Steamfitter, Refrigeration & Air Conditioning Mechanic$55.00$24.46
Sheet Metal Worker$53.42$23.20
Truck drivers: (HEAVY & HIGHWAY CONSTRUCTION) Tractor trailer, Low Boy$33.75$7.30
a Truck Drivers$31.75$7.30
Truck drivers: (PAVING & INCIDENTAL GRADING) All paving projects where the grading is incidental to the paving$31.75$7.30