Davis-Bacon
AZ20260034 (Rev 0)
Coverage: Arizona • Santa Cruz.
Published: Jan 02, 2026
Status: Active
Standard: Yes
Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| POWER EQUIPMENT OPERATOR: Drill Rig/Auger | $35.56 | $18.12 |
| Ironworker | $39.50 | $19.91 |
| Laborer: Asphalt, Includes Raker, Shoveler, Spreader and Distributor | $29.91 | $9.26 |
| Laborer: Mason Tender | $29.91 | $9.26 |
| Laborer: Pipelayer | $31.98 | $9.26 |
| Carpenter: Formwork Concrete | $32.51 | $10.13 |
| Laborer: General | $23.96 | $2.15 |
| Painter: Sign and Display Erector | $19.06 | $2.99 |
| Power Equipment Operator: Bobcat/Skid Steer/Skid Loader | $32.53 | $0.00 |
| Power Equipment Operator: Compactor/Roller | $26.76 | $4.76 |
| Power Equipment Operator: Concrete Screed | $33.90 | $0.00 |
| Power Equipment Operator: Crane / Derricks | $44.33 | $13.07 |
| Power Equipment Operator: Excavator/Trackhoe | $39.48 | $0.00 |
| Power Equipment Operator: Forklift | $38.31 | $9.20 |
| Power Equipment Operator: Loader/Front End Loader | $26.07 | $3.80 |
| Power Equipment Operator: Motor Grader/Blade | $36.47 | $3.61 |
| Power Equipment Operator: Oiler | $31.86 | $10.01 |
| Power Equipment Operator: Paver/Spreader/Finish equipment (asphalt, aggregate, & concrete) | $31.55 | $0.06 |
| Traffic Control | $19.38 | $2.54 |
| Truck Driver: Dump | $24.50 | $2.20 |
| Truck Driver: Water | $28.90 | $4.18 |