Davis-Bacon
AZ20260030 (Rev 0)
Coverage: Arizona • Graham.
Published: Jan 02, 2026
Status: Active
Standard: Yes
Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| POWER EQUIPMENT OPERATOR: Drill Rig/Auger | $35.56 | $18.12 |
| Ironworker | $39.50 | $19.91 |
| Laborer: Asphalt, Includes Raker, Shoveler, Spreader and Distributor | $29.91 | $9.26 |
| Laborer: Mason Tender | $29.91 | $9.26 |
| Laborer: Pipelayer | $31.98 | $9.26 |
| Carpenter: Formwork Concrete | $33.16 | $10.71 |
| Laborer: General | $32.28 | $6.98 |
| Painter: Sign and Display Erector | $19.06 | $2.99 |
| Power Equipment Operator: Bobcat/Skid Steer/Skid Loader | $32.53 | $0.00 |
| Power Equipment Operator: Compactor/Roller | $26.91 | $5.13 |
| Power Equipment Operator: Concrete Screed | $33.90 | $0.00 |
| Power Equipment Operator: Crane / Derricks | $47.73 | $13.07 |
| Power Equipment Operator: Excavator/Trackhoe | $39.48 | $0.00 |
| Power Equipment Operator: Forklift | $38.76 | $9.20 |
| Power Equipment Operator: Loader/Front End Loader | $39.20 | $0.00 |
| Power Equipment Operator: Motor Grader/Blade | $36.90 | $3.81 |
| Power Equipment Operator: Oiler | $31.86 | $10.01 |
| Power Equipment Operator: Paver/Spreader/Finish equipment (asphalt, aggregate, & concrete) | $30.40 | $0.06 |
| Traffic Control | $20.69 | $2.77 |
| Truck Driver: Dump | $24.50 | $2.75 |
| Truck Driver: Water | $29.52 | $3.47 |