Davis-Bacon
AK20260001 (Rev 0)
Coverage: Alaska • Anchorage, Bethel, Bristol Bay +16.
Published: Jan 02, 2026
Status: Active
Standard: Yes
Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| Asbestos Workers/Insulator (includes application of all insulating materials protective coverings, coatings and finishings to all types of mechanical systems) | $41.35 | $16.46 |
| TERIAL HANDLER (includes preparation, wetting, stripping, removal scrapping, vacuming, bagging, and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems) | $37.38 | $19.55 |
| BOILERMAKER | $58.33 | $28.79 |
| Bricklayer, Blocklayer, Stonemason, Marble Mason, Tile Setter, Terrazzo Worker | $52.77 | $12.36 |
| Tile & Terrazzo Finisher | $40.91 | $12.48 |
| CARPENTER Including Lather and Drywall Hanging | $50.79 | $26.42 |
| MILLWRIGHT | $56.44 | $25.87 |
| Diver Stand-by | $61.42 | $25.34 |
| Tender | $53.03 | $25.34 |
| Working | $92.83 | $26.42 |
| Piledriver Piledriver; Skiff Operator and Rigger | $48.72 | $26.42 |
| Sheet Stabber | $48.72 | $26.42 |
| Welder | $54.28 | $26.42 |
| ELEVATOR MECHANIC | $71.44 | $38.43 |
| POWER EQUIPMENT OPERATOR GROUP 1 | $53.23 | $29.50 |
| GROUP 1A | $55.33 | $29.50 |
| GROUP 2 | $52.32 | $29.50 |
| GROUP 3 | $51.46 | $29.50 |
| GROUP 4 | $44.06 | $29.50 |
| TUNNEL WORK GROUP 1 | $58.55 | $29.50 |
| GROUP 1A | $60.86 | $29.50 |
| GROUP 2 | $57.55 | $29.50 |
| GROUP 3 | $56.60 | $29.50 |
| GROUP 4 | $48.47 | $29.50 |
| IRONWORKER BENDER OPERATOR | $46.98 | $39.48 |
| BRIDGE, STRUCTURAL, ORNAMENTAL, REINFORCING MACHINERY MOVER, RIGGER, SHEETER, STAGE RIGGER, BENDER OPERATOR | $46.98 | $39.48 |
| FENCE, BARRIER INSTALLER | $43.48 | $39.48 |
| GUARDRAIL INSTALLERS | $44.48 | $39.48 |
| GUARDRAIL LAYOUT MAN | $44.22 | $39.48 |
| HELICOPTER, TOWER | $47.89 | $39.48 |
| LABORER (South of the 63rd Parallel & West of Longitude 138 Degrees) GROUP 1 | $40.25 | $34.26 |
| GROUP 2 | $41.25 | $34.26 |
| GROUP 3 | $42.15 | $34.26 |
| GROUP 3A | $46.53 | $34.26 |
| GROUP 3B | $54.01 | $28.81 |
| GROUP 4 | $29.82 | $34.26 |
| TUNNELS, SHAFTS, AND RAISES GROUP 1 | $44.28 | $34.26 |
| GROUP 2 | $45.38 | $34.26 |
| GROUP 3 | $46.37 | $34.26 |
| GROUP 3A | $51.18 | $34.26 |
| GROUP 3B | $59.41 | $28.81 |
| Laborers: North of the 63rd Parallel & East of Longitude 138 Degrees GROUP 1 | $40.25 | $34.26 |
| PAINTER BRUSH/ROLLER PAINT OR WALL COVERER | $43.05 | $26.45 |
| TAPING, TEXTURING, STRUCTURAL PAINTING, SANDBLASTING, POT TENDER, FINISH METAL, SPRAY, BUFFER OPERATOR, RADON MITIGATION, LEAD BASED PAINT ABATEMENT, HAZARDOUS MATERIAL HANDLER | $43.57 | $26.45 |
| PAINTER General Painter | $37.29 | $30.20 |
| Industrial Painter | $38.64 | $30.20 |
| Taper / Paper & Vinyl Hanger | $38.54 | $30.20 |
| GLAZIER | $46.76 | $30.46 |
| FLOOR LAYER: Carpet | $39.48 | $16.25 |
| GLAZIER | $47.42 | $29.10 |
| PLASTERER North of the 63rd parallel | $49.28 | $22.28 |
| South of the 63rd parallel | $49.28 | $22.28 |
| CEMENT MASON/CONCRETE FINISHER North of the 63rd parallel | $49.28 | $22.28 |
| Plumber; Steamfitter | $41.50 | $27.62 |
| Plumber; Steamfitter | $50.00 | $33.20 |
| Plumber; Steamfitter | $55.66 | $34.90 |
| SPRINKLER FITTER | $60.67 | $31.39 |
| ROOFER | $52.07 | $19.62 |
| SHEET METAL WORKER | $52.08 | $30.81 |
| SHEET METAL WORKER | $58.73 | $29.54 |
| TRUCK DRIVER GROUP 1 | $51.58 | $26.43 |
| GROUP 1A | $53.05 | $26.43 |
| GROUP 2 | $50.12 | $26.43 |
| GROUP 3 | $49.17 | $26.43 |
| GROUP 4 | $48.50 | $26.43 |
| GROUP 5 | $47.62 | $26.43 |