Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $40.00 | $23.65 |
| BOILERMAKER | $43.50 | $37.64 |
| TILE SETTER | $31.43 | $21.13 |
| PLASTERER | $33.09 | $26.58 |
| BRICKLAYER | $35.14 | $24.20 |
| CARPENTER (EXCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION, AND SOFT FLOOR LAYER - CARPET) | $35.86 | $23.69 |
| CARPENTER (ACOUSTICAL CEILING INSTALLATION, FORM WORK, METAL STUD INSTALLATION, AND LATHER DRYWALL HANGING) | $35.86 | $23.69 |
| MILLWRIGHT | $42.92 | $39.13 |
| ELECTRICIAN, LOW VOLTAGE WIRING ONLY (TECHNICIAN) | $37.62 | $14.80 |
| ELECTRICIAN, LOW VOLTAGE WIRING ONLY (INSTALLER) | $30.12 | $14.57 |
| ELECTRICIAN (EXCLUDES LOW VOLTAGE WIRING) | $51.32 | $28.44 |
| PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $31.23 | $25.25 |
| PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $33.71 | $25.25 |
| PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $39.57 | $25.25 |
| PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.28 | $25.25 |
| PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $43.93 | $25.25 |
| PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $47.28 | $25.25 |
| IRONWORKER: STRUCTURAL (METAL BUILDING ERECTION ONLY) | $30.02 | $27.43 |
| IRONWORKER, STRUCTURAL | $36.55 | $35.93 |
| IRONWORKER, REINFORCING | $36.55 | $33.37 |
| LABORER: SANDBLASTER | $26.73 | $13.45 |
| LABORER: COMMON OR GENERAL; MASON TENDER - BRICK; MASON TENDER - CEMENT/CONCRETE; AND PIPELAYER | $26.20 | $13.45 |
| PAINTER: DRYWALL FINISHING/TAPING | $23.79 | $12.02 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $23.79 | $12.02 |
| CEMENT MASON/CONCRETE FINISHER | $25.47 | $12.38 |
| PLUMBER: EXCLUDING HVAC PIPE AND SYSTEM INSTALLATION (PORTION OF HURON COUNTY LYING WEST OF M-53) | $43.50 | $22.10 |
| PIPEFITTER: HVAC PIPE INSTALLATION ONLY (PORTION OF HURON COUNTY LYING WEST OF M-53) | $45.50 | $21.75 |
| PIPEFITTER: EXCLUDES HVAC PIPE AND SYSTEM INSTALLATION (PORTION OF HURON COUNTY LYING WEST OF M-53) | $45.50 | $21.75 |
| PLUMBER: EXCLUDING HVAC PIPE & SYSTEM INSTALLATION (PORTION OF HURON COUNTY LYING EAST OF M-53) | $36.69 | $32.74 |
| PIPEFITTER: INCLUDES HVAC PIPE INSTALLATION; EXCLUDES HVAC SYSTEM INSTALLATION (PORTION OF HURON COUNTY LYING EAST OF M-53) | $41.96 | $40.85 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $41.34 | $27.39 |
| SHEET METAL WORKER (HVAC DUCT & SYSTEM INSTALLATION) | $26.83 | $23.78 |
| SHEET METAL WORKER (EXCLUDING HVAC DUCT & SYSTEM INSTALLATION) | $26.83 | $23.78 |
| TRUCK DRIVER: FLATBED TRUCK | $16.80 | $3.97 |
| TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK | $15.65 | $3.12 |
| ROOFER | $15.73 | $7.41 |
| OPERATOR: TRACTOR | $19.60 | $7.31 |
| OPERATOR: ROLLER | $28.02 | $7.07 |
| OPERATOR: GRADER/BLADE | $24.04 | $6.03 |
| OPERATOR: BULLDOZER | $22.34 | $1.22 |
| LABORER: LANDSCAPE & IRRIGATION | $12.84 | $0.00 |
| GLAZIER | $16.95 | $4.74 |
| CARPENTER (FLOOR LAYING-CARPET ONLY) | $19.59 | $7.57 |