Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| CARPENTER: HEAVY & HIGHWAY (DUPAGE ANE LAKE COUNTIES) | $52.01 | $38.85 |
| CARPENTER: BUILDING (DUPAGE ANE LAKE COUNTIES) | $52.01 | $38.85 |
| CARPENTER AND PILEDRIVER (WILL COUNTY) | $49.76 | $38.26 |
| CARPENTER AND PILEDRIVER (KANE, MCHENRY (NORTH OF HWY 52), AND KENDALL COUNTIES) | $52.01 | $38.86 |
| CARPENTER (DE KALB COUNTY) | $48.60 | $38.53 |
| CARPENTER (CARROLL, JO DAVIESS, LEE, OGLE (OREGON AND SOUTH THEREOF), STEPHENSON, AND WHITESIDE COUNTIES) | $48.60 | $38.53 |
| CARPENTER (BOONE COUNTY) | $51.00 | $36.13 |
| LINE CONSTRUCTION: LINEMAN AND EQUIPMENT OPERATOR (WILL COUNTY) | $62.10 | $37.29 |
| LINE CONSTRUCTION: GROUNDMAN (WILL COUNTY) | $48.44 | $29.09 |
| ELECTRICIAN (KANE (NORTHERN HALF) AND MCHENRY (ALL) COUNTIES) | $59.11 | $42.23 |
| ELECTRICIAN (LAKE COUNTY) | $48.28 | $50.46 |
| ELECTRICIAN (WILL COUNTY) | $52.00 | $45.01 |
| R 20 TONS AND ABOVE, AND SIGNAL TECHNICIAN (BOONE, DEKALB, DUPAGE, KANE, KENDALL, LAKE, AND MCHENRY COUNTIES) FOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, AND THANKSGIVING DAY | $59.17 | $27.12 |
| LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (BOONE, DEKALB, DUPAGE, KANE, KENDALL, LAKE, AND MCHENRY COUNTIES) FOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, AND THANKSGIVING DAY | $39.19 | $20.32 |
| LINE CONSTRUCTION: GROUNDMAN (BOONE, DEKALB, DUPAGE, KANE, KENDALL, LAKE, AND MCHENRY COUNTIES) FOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, AND THANKSGIVING DAY | $37.81 | $19.86 |
| LINE CONSTRUCTION: EQUIPMENT OPERATOR (BOONE, DEKALB, DUPAGE, KANE, KENDALL, LAKE, AND MCHENRY COUNTIES) FOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, AND THANKSGIVING DAY | $49.22 | $23.73 |
| ELECTRICIAN (BOONE (ALL) & DEKALB (REMAINDER) COUNTIES) | $62.61 | $43.96 |
| ELECTRICIAN (DEKALB (SANDWICH TWP), KANE (SOUTHERN HALF) & KENDALL (ALL) COUNTIES) | $60.17 | $43.50 |
| ELECTRICIAN (DUPAGE COUNTY) | $41.00 | $43.40 |
| OPERATOR: POWER EQUIPMENT, GROUP 5 OILERS (BOONE AND DE KALB COUNTIES) | $50.85 | $51.05 |
| PER HOUR | $53.30 | $51.05 |
| PER HOUR | $54.75 | $51.05 |
| PER HOUR. (BOONE AND DE KALB COUNTIES) | $56.05 | $51.05 |
| PER HOUR | $56.60 | $51.05 |
| OPERATOR: POWER EQUIPMENT, GROUP 5 BOBCATS (ALL); BRICK FORKLIFTS; OILERS; DIRECTIONAL BORING (DUPAGE, KANE, KENDALL, LAKE, MCHENRY, AND WILL COUNTIES) | $57.80 | $51.00 |
| TO 3, NOT TO EXCEED A TOTAL OF 300 FT); PUMPS, WELL POINTS; TRACTAIRE; WELDING MACHINES (2 THROUGH 5); WINCHES, 4 SMALL ELECTRIC DRILL WINCHES; (DUPAGE, KANE, KENDALL, LAKE, MCHENRY, AND WILL COUNTIES) | $59.00 | $51.00 |
| RS, OTHER THAN ASPHALT; SEED AND STRAW BLOWER; STEAM GENERATORS; STUMP MACHINE; WINCH TRUCKS WITH A-FRAME; WORK BOATS; TAMPER-FORM MOTOR DRIVEN (DUPAGE, KANE, KENDALL, LAKE, MCHENRY, AND WILL COUNTIES) | $60.40 | $51.00 |
| REQUIRES OILER | $62.45 | $51.00 |
| DUPAGE, KANE, KENDALL, LAKE, MCHENRY, AND WILL COUNTIES) | $63.00 | $51.00 |
| IRONWORKER: STRUCTURAL AND REINFORCING (DU PAGE (EASTERN 1/4), LAKE, AND MCHENRY (HEBRON, WOODSTOCK, AND EAST THEREOF) COUNTIES) | $62.46 | $46.58 |
| IRONWORKER: SHEETER (DU PAGE (EASTERN 1/4), LAKE, AND MCHENRY (HEBRON, WOODSTOCK, AND EAST THEREOF) COUNTIES) | $62.71 | $46.58 |
| IRONWORKER, ORNAMENTAL (LAKE, DUPAGE (EASTERN 1/4) AND MCHENRY (HEBRON, WOODSTOCK & EAST THEREOF) COUNTIES) | $59.26 | $44.81 |
| IRONWORKER (DEKALB (SOUTHEASTERN 2/3 INCLUDING SYCAMORE AND DEKALB), DUPAGE (REMAINDER), KANE, KENDALL (NORTHERN PART), AND MCHENRY (SOUTHEAST 1/4) COUNTIES) | $48.83 | $39.84 |
| IRONWORKER (KENDALL (SOUTHERN PART) AND WILL COUNTIES) | $47.80 | $42.50 |
| IRONWORKER (BOONE, DEKALB (EXCEPT SOUTHEAST), AND MCHENRY (NORTHWEST) COUNTIES) | $41.37 | $44.41 |
| LABORER, SEWER CONSTRUCTION: GROUP 5 ASBESTOS ABATEMENT LABORERS, TOXIC AND HAZARDOUS WASTE REMOVAL LABORERS & DOSIMETER USE (ANY DEVICE) MONITORING NUCLEAR EXPOSURE. (DUPAGE COUNTY) | $51.40 | $36.94 |
| M MEN; BRACERS-BRACING; BRICKLAYER'S TENDER; CATCH BASIN DIGGER; DRAINLAYER; DYNAMITER; FORM MEN; JACKHAMMERMEN; POWERPAC; PIPELAYERS; RODDERS; WELDERS & BURNERS; WELL POINT SYSTEM MEN. (DUPAGE COUNTY) | $51.75 | $36.94 |
| LABORER, SEWER CONSTRUCTION: GROUP 3 CEMENT CARRIERS; CEMENT MIXERS; CONCRETE REPAIRMEN; MORTAR MEN; SCAFFOLD MEN; AND SECOND BOTTOM MEN. (DUPAGE COUNTY) | $51.63 | $36.94 |
| LABORER, SEWER CONSTRUCTION: GROUP 2 CONCRETE LABORERS; STEEL SETTERS. (DUPAGE COUNTY) | $51.53 | $36.94 |
| LABORER, SEWER CONSTRUCTION: GROUP 1 SIGNALMEN TOP LABORERS, AND ALL OTHER LABORERS NOT MENTIONED. (DUPAGE COUNTY) | $51.40 | $36.94 |
| LABORER, TUNNEL: GROUP 5 ASBESTOS ABATEMENT LABORER; TOXIC AND HAZARDOUS WASTE REMOVAL LABORER; DOSIMETER (ANY DEVICE) MONITORING NUCLEAR EXPOSURE (DUPAGE COUNTY) | $51.40 | $36.94 |
| CHINE OPERATOR; LASER BEAM OPERATOR; LINER PLATE AND RING SETTERS; SHIELD DRIVERS; POWER KNIFE OPERATOR; WELDER- BURNERS; PIPE JACKING MACHINE OPERATOR; SKINNERS; MAINTENANCE TECHNICIAN (DUPAGE COUNTY) | $51.75 | $36.94 |
| LABORER, TUNNEL: GROUP 3 CONCRETE REPAIRMEN; LOCK TENDERS (PRESSURE SIDE); MORTAR MEN; MUCKERS; GROUT MACHINE OPERATORS; TRACK LAYERS (DUPAGE COUNTY) | $51.63 | $36.94 |
| LABORER, TUNNEL: GROUP 2 AIR HOIST OPERATOR; KEY BOARD OPERATOR; CONCRETE LABORER; GROUT; LOCK TENDERS (FREE AIR SIDE); STEEL SETTERS; TUGGERS; SWITCHMEN; CAR PUSHER (DUPAGE COUNTY) | $51.53 | $36.94 |
| LABORER, TUNNEL: GROUP 1 CAGE TENDERS; DUMPMEN; FLAGMEN; SIGNALMEN; TOP LABORERS (DUPAGE COUNTY) | $51.40 | $36.94 |
| LABORER, COMPRESSED AIR: 34 LBS AND OVER (DU PAGE COUNTY) | $55.40 | $36.94 |
| LABORER, COMPRESSED AIR, 0-15 lbs (DU PAGE COUNTY) | $52.40 | $36.94 |
| BURNING MACHINE OPERATOR, CORING MACHINE OPERATOR, PLASTER TENDER, UNDERPINNING & SHORING OF BUILDINGS, PUMP MAN, MANHOLE & CATCH BASIN, DIRT & STONE TAMPER, HOSEMAN ON CONCRETE PUMP. (DE KALB COUNTY) | $50.39 | $36.31 |
| KES, STRINGLINES FOR ALL MACHINERY, WINDOW CLEANING, DEMOLITION WORKER, EXPLOSIVE HANDLING, TRIMMING & REMOVAL OF TREES, MULTI-PLATE PIPE, PILOT CARS FOR TRAFFIC CONTROL, POWER RIGGING (DE KALB COUNTY) | $47.04 | $36.31 |
| NUCLEAR EXPOSURE; ASBESTOS ABATEMENT WORKER; TOXIC AND HAZARDOUS WASTE REMOVAL LABORER; AND CHIMNEY AND SILO LABORERS FOR EVERY ADDITIONAL 50 FEET OR ANY PART THEREOF ABOVE 100 FEET HIGH (WILL COUNTY) | $51.60 | $36.94 |
| LABORER GROUP 6 ALL UNDERGROUND CAVERN LABORERS; CAISSON LABORERS 50 FEET OR MORE BELOW GROUND LEVEL; LABORERS WORKING UNDER RADIO ACTIVE CONDITIONS (SUITING UP); BLASTING MEN (POWDERMEN) (WILL COUNTY) | $51.75 | $36.94 |
| OF TANK AT A HEIGHT OF 48 FEET TO 100 FEET; ALL HYDRAULIC, ELECTRIC AND AIR TOOLS OR ANY OTHER TYPE 8 FEET OR MORE BELOW GROUND LEVEL; VIBRATORS-ANY TYPE-8 FEET OR MORE BELOW GROUND LEVEL (WILL COUNTY) | $51.75 | $36.94 |
| MENTIONED WORK; WAGON AND TOWER DRILLERS ON LAND AND FLOATING PLANT USED ON DREDGING; ASPHALT GUNNERS AND PLUG MEN (UNDERCOATING ON ROAD WORK); MORTAR PUMP LABORERS; PLASTER PUMP LABORERS (WILL COUNTY) | $51.40 | $36.94 |
| LABORER GROUP 2 SEWER AND DRAIN PIPE LAYERS AND MULTIPLE CONCRETE DUCT OR ANY OTHER TYPE OF PIPE USED, ON PUBLIC UTILITY WORK (GROUND LEVEL TO 8 FEET); PUMPCRETE PIPE HANDLERS (WILL COUNTY) | $51.75 | $36.94 |
| LEANING OF DEBRIS; REMOVAL OF TREES; CONCRETE CURING, TEMPORARY CONCRETE PROTECTION REGARDLESS OF MANNER OR MATERIALS USED; LABORERS ON APSCO; JANITORIAL; WRECKING AND DEMOLITION LABORERS (WILL COUNTY) | $51.40 | $36.94 |
| LABORER GROUP 9 ASBESTOS APATEMENT LABORERS, TOXIC & HAZARDOUS WASTE REMOVAL LABORERS & DOSIMETER (ANY DEVICE) MONITORING NUCLEAR EXPOSURE (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $52.40 | $36.94 |
| LABORER GROUP 8 FLAGMAN (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.40 | $36.94 |
| LABORER GROUP 7 CAISSON DIGGERS, DYNAMITERS (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.75 | $36.94 |
| LABORER GROUP 6 TUNNEL LABORERS, TILE LAYERS & BOTTOM MEN (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.75 | $36.94 |
| LABORER GROUP 5 CHAIN SAW MAN, JACKHAMMER MAN, DRILLMAN, CONCRETE BREADERS & AIR SPADE (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.63 | $36.94 |
| LABORER GROUP 4 STRINGLINE & FORM SETTER; TORCHMAN (DEMOLITION), SHEETING & CRIBBING, BLACK TOP RAKERS & LUTEMEN, MACHINE SCREWMEN (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.68 | $36.94 |
| LABORER GROUP 3 MORTAR & CONCRETE MIXERS (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.68 | $36.94 |
| LABORER GROUP 2 AIR TAMPERS & VIBRATORS (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.68 | $36.94 |
| LABORER GROUP 1 COMMON LABORER, ASPHALT LABORER, ASPHALT PLANT LABORER, STRIPING LABORER, CLIPPER TYPE CONCRETE SAW, SELF-PROPELLED SAWS (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.40 | $36.94 |
| LABORER GROUP 6 ASBESTOS ABATEMENT LABORERS; TOXIC AND HAZARDOUS WASTE REMOVAL LABORERS; DOSIMETER (ANY DEVICE MONITORING NUCLEAR EXPOSURE) (LAKE COUNTY) | $51.60 | $36.94 |
| LABORER GROUP 5 CEMENT GUN NOZZLE (GUNITE) (LAKE COUNTY) | $51.60 | $36.94 |
| LABORER GROUP 3 ASPHALT TAMPERS AND SMOOTHERS (LAKE COUNTY) | $51.40 | $36.94 |
| LABORER GROUP 2 CEMENT GUN LABORERS (LAKE COUNTY) | $51.48 | $36.94 |
| LABORER GROUP 1 GENERAL LABORERS; ASPHALT (LAKE COUNTY) | $51.40 | $36.94 |
| PAINTER: BRUSH ONLY (LAKE AND WILL COUNTIES) | $53.05 | $33.91 |
| PAINTER: BRUSH, DRYWALL TAPER/FINISHER, SANDBLASTER, AND SPRAY (DE KALB, DU PAGE, KANE, KENDALL AND MCHENRY COUNTIES) | $53.05 | $27.63 |
| PAINTER: BRUSH, ROLLER, SPRAY, SANDBLASTING, PAPERHANGER, DRYWALL FINISHING, TAPER, AND SPRAY STRUCTURAL STEEL (BOONE, JO DAVIESS, LEE, OGLE, STEPHENSON AND WINNEBAGO COUNTIES) | $45.15 | $29.41 |
| CEMENT MASON/CONCRETE FINISHER (WILL COUNTY) | $46.25 | $45.10 |
| CEMENT MASON/CONCRETE FINISHER (DE KALB, KANE, KENDALL, AND MCHENRY COUNTIES) | $50.70 | $40.60 |
| CEMENT MASON/CONCRETE FINISHER (LAKE COUNTY) | $48.50 | $42.82 |
| PLASTERER (BOONE COUNTY) | $37.90 | $37.66 |
| CEMENT MASON/CONCRETE FINISHER (BOONE COUNTY) | $41.03 | $36.39 |
| CEMENT MASON/CONCRETE FINISHER (DUPAGE COUNTY) | $38.00 | $24.03 |
| PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES | $46.67 | $0.30 |
| PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES | $46.47 | $0.30 |
| PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES | $46.27 | $0.30 |
| PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES | $46.12 | $0.30 |
| AIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $45.09 | $13.40 |
| AIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $44.89 | $13.40 |
| AIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $44.69 | $13.40 |
| AIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $44.54 | $13.40 |
| PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES | $48.93 | $26.70 |
| PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES | $48.82 | $26.70 |
| PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES | $48.62 | $26.70 |
| PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES | $48.47 | $26.70 |
| AIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $45.38 | $0.30 |
| AIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $45.18 | $0.30 |
| AIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $44.98 | $0.30 |
| AIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $44.83 | $0.30 |
| AIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $45.86 | $0.30 |
| AIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $45.66 | $0.30 |
| AIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $45.46 | $0.30 |
| AIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $45.31 | $0.30 |
| MENT MARKINGS, BARRICADES, CRASH BARRELS AND GLARE SCREENS, TRAFFIC CONTROL SURVEILLANCE, THE REPAIR AND MAINTENANCE TRUCKS, CARS, ARROW BOARDS, MESSAGE SIGNS, BARRICADE AND SIGN FABRICATION EQUIPMENT) | $43.40 | $22.71 |
Related Wage Determinations
View directory →Davis-Bacon
IL20260006 (Rev 1)
Illinois • Kankakee
Davis-Bacon
IL20260007 (Rev 2)
Illinois • Madison, St Clair
Davis-Bacon
IL20260049 (Rev 2)
Illinois • Montgomery
Davis-Bacon
IL20260010 (Rev 1)
Illinois • Winnebago
Davis-Bacon
IL20260019 (Rev 1)
Illinois • Adams, Alexander, Bond +99
Davis-Bacon
IL20260022 (Rev 2)
Illinois • Hamilton